7331 N RUBIO AVE 91406

Certificate Information: 7331 N RUBIO AVE 91406

Application / Permit
21014-20000-04536
Plan Check / Job No.
B21VN12116
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20'1" X 13' ADDITION TO AND CONVERT THE (E) 20'1" X 18'1" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT AS PER LAMC 12.21A.33 (C) AND (D), ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
CofO Issued on 12/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Assigned to Plan Check Engineer 9/20/2021 RARES BODEA
Corrections Issued 9/20/2021 RARES BODEA
Building Plans Picked Up 9/22/2021 APPLICANT
Applicant returned to address corrections 3/7/2022 RARES BODEA
Plan Check Approved 3/29/2022 RARES BODEA
Issued 4/25/2022 APPLICANT
CofO in Progress 11/19/2024 SALVADOR MARTINEZ
Permit Finaled 12/10/2024 RUBEN SALAS
CofO Issued 12/10/2024 RUBEN SALAS
Permit Finaled 12/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/1/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/1/2021 CARLOS AGUILERA
Sewer availability Cleared 11/8/2021 CARLOS AGUILERA
Construction near power lines Cleared 2/15/2022 RIDWAN HARDY
Construction within easement Cleared 2/15/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/15/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/16/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 11/16/2022 Approved RAUL OLAGI
PLUMBING-Rough 11/16/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Corrections Issued RAUL OLAGI
Green Building Rough 2/10/2023 Not Ready for Inspection RAUL OLAGI
Rough-Elec/Plmb/HVAC 2/10/2023 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 2/14/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/14/2023 Approved RAUL OLAGI
HVAC-Rough 2/14/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 2/14/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 4/13/2023 Approved RAUL OLAGI
Green Building Rough 4/13/2023 Approved RAUL OLAGI
HVAC-Rough 4/13/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 4/13/2023 Partial Approval RAUL OLAGI
Insulation 4/21/2023 Approved RAUL OLAGI
Drywall Nailing 5/5/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 5/5/2023 Approved RAUL OLAGI
Pre-Inspection 9/28/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 4/18/2024 Approved RAUL OLAGI
Sewer 4/18/2024 Corrections Issued RAUL OLAGI
Underground Mechanical 4/18/2024 Corrections Issued RAUL OLAGI
Underground Mechanical 5/17/2024 Not Ready for Inspection SALVADOR MARTINEZ
Underground Mechanical 5/21/2024 Approved MICHEL ABAJAN
Final 7/25/2024 Corrections Issued RAUL OLAGI
Green Building Final 7/25/2024 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 7/25/2024 Approved RAUL OLAGI
Final 10/3/2024 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV Not Ready MATTHEW NELSON
Final 10/18/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 10/18/2024 SGSOV Approved SALVADOR MARTINEZ
Final 11/15/2024 OK to Issue CofO SALVADOR MARTINEZ