17849 W DUNCAN ST 91316
Certificate Information: 17849 W DUNCAN ST 91316
- Application / Permit
- 21014-20000-04535
- Plan Check / Job No.
- B21VN12115
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 0PROVIDE 18'-1" X 47'-5" IRREGULAR SHAPED ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- Issued on 4/21/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/14/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/4/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 3/28/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Issued | 4/21/2022 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/22/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/23/2021 | LEE GUILBEAUX |
| ZI | Cleared | 9/29/2021 | DANIEL CORONADO |
| Low Impact Development | Cleared | 2/24/2022 | JULIAN SUNG |
| Construction near power lines | Cleared | 3/5/2022 | JOHN BACON |
| Roof/Waste drainage to street | Cleared | 3/25/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/8/2022 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 7/1/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 7/26/2022 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | No Access for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2022 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 2/3/2023 | Partial Approval | JEFFREY BULL |
| Rough-Elec/Plmb/HVAC | 2/3/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 2/13/2023 | No Access for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/22/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 2/22/2023 | Approved | JEFFREY BULL |
| Insulation | 3/2/2023 | No Access for Inspection | JEFFREY BULL |
| Insulation | 3/8/2023 | Corrections Issued | JEFFREY BULL |
| Drywall Nailing | 3/29/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 3/29/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 6/20/2023 | Not Ready for Inspection | JEFFREY BULL |
| Final | 6/20/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 6/20/2023 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Final | 6/20/2023 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Final | 6/20/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 6/20/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 6/20/2023 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 6/20/2023 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Final | 10/26/2023 | Approved | JEFFREY BULL |
| Final | 10/26/2023 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Final | 10/26/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 10/26/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 10/26/2023 | Approved | JEFFREY BULL |