15448 W SAN JOSE ST 91345
Certificate Information: 15448 W SAN JOSE ST 91345
- Application / Permit
- 21014-20000-04533
- Plan Check / Job No.
- B21VN12107
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (22'-0"x24'-0"),487 SQFT ADDITION OF AN ATTACHED 2 CAR GARAGE TO THE (E) SFD.
- Permit Issued
- Issued on 12/27/2021
- Issuing Office
- Current Status
- CofO Issued on 8/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | PETER MOSESIAN |
| Corrections Issued | 9/9/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 9/10/2021 | APPLICANT |
| Applicant returned to address corrections | 10/11/2021 | PETER MOSESIAN |
| Plan Check Approved | 11/29/2021 | PETER MOSESIAN |
| Issued | 12/27/2021 | APPLICANT |
| CofO in Progress | 7/27/2022 | JENNIFER RABUCHIN |
| Permit Finaled | 8/9/2022 | DEROLD HAUFF |
| CofO Issued | 8/9/2022 | DEROLD HAUFF |
| Permit Finaled | 8/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/21/2021 | CARLOS AGUILERA |
| Watercourse | Cleared | 9/21/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/24/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 4/12/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/6/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 5/6/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 5/6/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Drywall Nailing | 5/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 5/20/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/20/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 5/25/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/13/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/13/2022 | Approved | JENNIFER RABUCHIN |
| Final | 7/13/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/13/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 7/13/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 7/13/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 7/13/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/13/2022 | Approved | JENNIFER RABUCHIN |