6901-6903 N VARIEL AVE 91303
Certificate Information: 6901-6903 N VARIEL AVE 91303
- Application / Permit
- 21014-20000-04530
- Plan Check / Job No.
- B21VN12090
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 477 SQFT ADDITION FOR NEW BEDROOM/BATHROOM TO THE EX DWELLING AND CONNECT TO DETACHED GARAGE. CONVERT 20'1" x 29'3" (IRR. SHAPE) LIVING ROOM INTO A (N) JR. ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) and 65852.22. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/15/2021
- Issuing Office
- Current Status
- CofO Issued on 7/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2021 | JEFFREY TANGONAN |
| Corrections Issued | 9/11/2021 | JEFFREY TANGONAN |
| Issued | 10/15/2021 | APPLICANT |
| Building Plans Picked Up | 10/15/2021 | APPLICANT |
| CofO in Progress | 6/30/2022 | DAVID SCANTLIN |
| Permit Finaled | 7/20/2022 | JOHN JANSON |
| CofO Issued | 7/20/2022 | JOHN JANSON |
| Permit Finaled | 7/20/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Permit | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/15/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/2/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 12/2/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 1/18/2022 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 1/18/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 1/18/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 1/18/2022 | Approved | STEVEN BACK |
| Special/Order Compliance | 1/18/2022 | Corrections Issued | STEVEN BACK |
| Deputy Wood Construction | 1/19/2022 | Conditional Approval | JESUS PINEDA |
| HVAC-Rough | 1/27/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 1/27/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 2/2/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 2/2/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 2/4/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 2/4/2022 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 2/22/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Approved | STEVEN BACK |
| Green Building Rough | 2/22/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 2/22/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 2/22/2022 | Approved | STEVEN BACK |
| Insulation | 2/28/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 3/7/2022 | Approved | STEVEN BACK |
| Final | 5/27/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 5/27/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 5/27/2022 | Corrections Issued | STEVEN BACK |
| Final | 6/10/2022 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 6/10/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 6/29/2022 | Approved | DAVID SCANTLIN |
| Final | 6/29/2022 | OK to Issue CofO | DAVID SCANTLIN |
| PLUMBING-Final | 6/29/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Approved | DAVID SCANTLIN |