14917 W SYLVAN ST 91411
Certificate Information: 14917 W SYLVAN ST 91411
- Application / Permit
- 21014-20000-04528
- Plan Check / Job No.
- B21VN12079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 15'-10" X 5'-5" ADDITION TO THE (E) SFD AND CHANGE OUT (11) WINDOWS, SAME SIZE. WORK PER WFPP.
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2021 | OMAR GARNICA |
| Corrections Issued | 9/8/2021 | OMAR GARNICA |
| Plan Check Approved | 9/21/2021 | JENNIFER LEE |
| Building Plans Picked Up | 9/21/2021 | APPLICANT |
| Issued | 9/30/2021 | APPLICANT |
| CofO in Progress | 8/9/2022 | RICHARD DOCKUS |
| Permit Finaled | 8/17/2022 | RONALD MYRICK |
| CofO Issued | 8/17/2022 | RONALD MYRICK |
| Permit Finaled | 8/17/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/9/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/15/2021 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 10/15/2021 | Approved | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 10/15/2021 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/15/2021 | Partial Approval | ALAN MORELOS |
| Special/Order Compliance | 10/15/2021 | Partial Inspection | CALEB MEISTER |
| Special/Order Compliance | 10/15/2021 | Partial Inspection | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/4/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 11/4/2021 | Partial Approval | RICHARD DOCKUS |
| Underground Mechanical | 11/4/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 3/29/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/29/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 3/29/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Insulation | 3/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 4/6/2022 | Corrections Issued | ALAN MORELOS |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | ALAN MORELOS |
| PLUMBING-Rough | 4/6/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 4/12/2022 | Approved | ALAN MORELOS |
| Green Building Rough | 4/12/2022 | Approved | ALAN MORELOS |
| Insulation | 4/12/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 4/19/2022 | Approved | ALAN MORELOS |
| Shower Pan | 4/19/2022 | Approved | ALAN MORELOS |
| Gas Test | 4/25/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| PLUMBING-Rough | 7/7/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 7/7/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 7/7/2022 | Approved | RICHARD DOCKUS |
| Final | 7/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Final | 7/29/2022 | Approved | JENNIFER RABUCHIN |
| Final | 8/8/2022 | OK to Issue CofO | RICHARD DOCKUS |