12800 N NEON WAY 91344
Certificate Information: 12800 N NEON WAY 91344
- Application / Permit
- 21014-20000-04517
- Plan Check / Job No.
- B21VN12056
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & 2ND FLOOR ADDITION TO THE (E) SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO Issued on 5/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | COLIN LOREDO |
| Corrections Issued | 10/12/2021 | COLIN LOREDO |
| Quality Review Completed | 10/20/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 11/18/2021 | COLIN LOREDO |
| Plan Check Approved | 1/18/2022 | COLIN LOREDO |
| Issued | 4/1/2022 | APPLICANT |
| CofO in Progress | 5/1/2024 | DAVID SCANTLIN |
| Permit Finaled | 5/22/2024 | JOHN JANSON |
| CofO Issued | 5/22/2024 | JOHN JANSON |
| Permit Finaled | 5/22/2024 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/13/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 10/13/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 10/13/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 10/13/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 10/13/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 10/13/2021 | DANG NGUYEN |
| Sewer availability | Cleared | 10/13/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 10/13/2021 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 11/18/2021 | ALEXANDER ANDREWS |
| Roof/Waste drainage to street | Cleared | 11/18/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 1/5/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Advanced Construction; Lic. No.: 801955-B | 4606 WILLIS AVE #307 SHERMAN OAKS, CA 91403 |
| Engineer | Grigoryan,, Souren Krist; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/13/2022 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/18/2022 | Approved | DAVID SCANTLIN |
| Deputy Steel/Welding | 5/31/2022 | Conditional Approval | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2022 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 11/29/2022 | Corrections Issued | DAVID SCANTLIN |
| HVAC-Rough | 11/29/2022 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 11/30/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 11/30/2022 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 12/7/2022 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 12/16/2022 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 12/16/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 12/16/2022 | Not Ready for Inspection | STEVEN BACK |
| Verify Sprinkler Sign Off | 12/16/2022 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 1/5/2023 | Approved | SEAN HAUPT |
| HVAC-Rough | 1/5/2023 | Approved | SEAN HAUPT |
| Insulation | 1/5/2023 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 1/5/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 1/24/2023 | Approved | SEAN HAUPT |
| Shower Pan | 4/12/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 5/1/2023 | Approved | DAVID SCANTLIN |
| Gas Test | 8/15/2023 | Approved | HENRY KIM |
| Underground Mechanical | 8/15/2023 | Approved | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Not Ready | STEVEN BACK |
| Special/Order Compliance | 9/20/2023 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Approved | DAVID SCANTLIN |
| Final | 4/26/2024 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 4/26/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 4/26/2024 | Approved | DAVID SCANTLIN |
| Final | 5/1/2024 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 5/1/2024 | Approved | DAVID SCANTLIN |