4485 N MATILIJA AVE 91423
Certificate Information: 4485 N MATILIJA AVE 91423
- Application / Permit
- 21014-20000-04515
- Plan Check / Job No.
- B21VN12053
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION (IRREGULAR SHAPED) TO (E) SFD; INTERIOR REMODEL
- Permit Issued
- Issued on 6/28/2022
- Issuing Office
- Current Status
- CofO Issued on 5/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/14/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/16/2021 | STEVEN KIM |
| Building Plans Picked Up | 9/22/2021 | APPLICANT |
| Applicant returned to address corrections | 5/25/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/17/2022 | NILOOFAR MEHRAIN |
| Issued | 6/28/2022 | APPLICANT |
| CofO in Progress | 5/1/2025 | MISAEL ESPARZA |
| CofO Issued | 5/2/2025 | RUBEN SALAS |
| Permit Finaled | 5/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/21/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 3/5/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 4/6/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 4/28/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Carlee Construction Inc; Lic. No.: 500519-B | 18225 RANCHO STREET TARZANA, CA 91356 |
| Engineer | Luisoni,, Antonio Stefano; Lic. No.: S1781 | 12757 DEON PLACE GRANADA HILLS, CA 91344 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/13/2022 | Conditional Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 9/14/2022 | Conditional Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 9/21/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/30/2022 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 3/10/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/24/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 3/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 5/1/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 5/1/2023 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/9/2023 | Partial Approval | JOHN COLEMAN |
| ELECTRICAL-Rough | 6/20/2023 | Approved | JOHN COLEMAN |
| HVAC-Rough | 6/20/2023 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 6/20/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/23/2023 | Approved | JOHN COLEMAN |
| Deputy Wood Construction | 6/23/2023 | Conditional Approval | JUAN VALENZUELA |
| Green Building Rough | 6/23/2023 | Approved | JOHN COLEMAN |
| Insulation | 7/12/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 7/31/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/19/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 9/19/2023 | Approved | MISAEL ESPARZA |
| Final | 2/21/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 2/21/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 2/21/2024 | Approved | MISAEL ESPARZA |
| Final | 3/14/2024 | Conditional Approval | MISAEL ESPARZA |
| Green Building Final | 3/14/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Approved | MISAEL ESPARZA |
| Final | 3/21/2024 | Corrections Issued | MISAEL ESPARZA |
| Final | 5/1/2025 | OK to Issue CofO | MISAEL ESPARZA |