4485 N MATILIJA AVE 91423

Certificate Information: 4485 N MATILIJA AVE 91423

Application / Permit
21014-20000-04515
Plan Check / Job No.
B21VN12053
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-STORY ADDITION (IRREGULAR SHAPED) TO (E) SFD; INTERIOR REMODEL
Permit Issued
Issued on 6/28/2022
Issuing Office
Current Status
CofO Issued on 5/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 NILOOFAR MEHRAIN
Corrections Issued 9/14/2021 NILOOFAR MEHRAIN
Quality Review Completed 9/16/2021 STEVEN KIM
Building Plans Picked Up 9/22/2021 APPLICANT
Applicant returned to address corrections 5/25/2022 NILOOFAR MEHRAIN
Plan Check Approved 6/17/2022 NILOOFAR MEHRAIN
Issued 6/28/2022 APPLICANT
CofO in Progress 5/1/2025 MISAEL ESPARZA
CofO Issued 5/2/2025 RUBEN SALAS
Permit Finaled 5/2/2025 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 1/21/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/25/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 3/5/2022 CINDY JOSSELYN
Low Impact Development Cleared 4/6/2022 TA ANH
Roof/Waste drainage to street Cleared 4/28/2022 ABDULLAH SADOZAI

Contact Information

Contractor Carlee Construction Inc; Lic. No.: 500519-B 18225 RANCHO STREET      TARZANA, CA 91356
Engineer Luisoni,, Antonio Stefano; Lic. No.: S1781 12757 DEON PLACE      GRANADA HILLS, CA 91344

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/13/2022 Conditional Approval MISAEL ESPARZA
Deputy Wood Construction 9/14/2022 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 9/21/2022 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/30/2022 Approved MISAEL ESPARZA
Deputy Wood Construction 3/10/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 3/24/2023 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Partial Approval MISAEL ESPARZA
Green Building Rough 3/24/2023 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Partial Approval MISAEL ESPARZA
Green Building Rough 5/1/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 5/1/2023 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 6/9/2023 Partial Approval JOHN COLEMAN
ELECTRICAL-Rough 6/20/2023 Approved JOHN COLEMAN
HVAC-Rough 6/20/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 6/20/2023 Approved JOHN COLEMAN
BUILDING-Rough-Frame 6/23/2023 Approved JOHN COLEMAN
Deputy Wood Construction 6/23/2023 Conditional Approval JUAN VALENZUELA
Green Building Rough 6/23/2023 Approved JOHN COLEMAN
Insulation 7/12/2023 Approved RYAN SALAZAR
Drywall Nailing 7/31/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/19/2023 Approved MISAEL ESPARZA
Shower Pan 9/19/2023 Approved MISAEL ESPARZA
Final 2/21/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 2/21/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/21/2024 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 2/21/2024 Approved MISAEL ESPARZA
Final 3/14/2024 Conditional Approval MISAEL ESPARZA
Green Building Final 3/14/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Approved MISAEL ESPARZA
Final 3/21/2024 Corrections Issued MISAEL ESPARZA
Final 5/1/2025 OK to Issue CofO MISAEL ESPARZA