3940 N DRYSDALE AVE 90032

Certificate Information: 3940 N DRYSDALE AVE 90032

Application / Permit
21014-20000-04512
Plan Check / Job No.
B21VN12045
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
21' X 17'-11" ADDITION FOR NEW BEDROOM, LAUNDRY ROOM, AND TWO NEW BATHROOMS PER WFPP.
Permit Issued
Issued on 9/23/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Assigned to Plan Check Engineer 9/21/2021 SARKIS HARABEDIAN
Corrections Issued 9/27/2021 SARKIS HARABEDIAN
Building Plans Picked Up 9/28/2021 APPLICANT
Plan Check Approved 9/22/2022 JEROME MAGAT PALMA
Issued 9/23/2022 APPLICANT
CofO in Progress 6/14/2024 LILIANA PORTILLO
Permit Finaled 6/27/2024 DEROLD HAUFF
Permit Finaled 6/27/2024 DEROLD HAUFF
CofO Issued 6/27/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/2/2021 ROBERT HUGHES
Eng Process Fee Ord 176,300 Cleared 10/4/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 10/4/2021 RENZ SORIANO
Sewer availability Cleared 10/4/2021 RENZ SORIANO
Hydrant and Access approval Cleared 11/2/2021 MATTHEW CRAIG
"D" conditions Cleared 8/8/2022 CLAUDE GOODING
"Q" conditions Cleared 8/8/2022 CLAUDE GOODING

Contact Information

No Data Available.

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/16/2022 Approved AMY COLIN
PLUMBING-Rough 11/23/2022 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Partial Approval AMY COLIN
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Partial Approval AMY COLIN
Insulation 12/20/2022 Partial Approval AMY COLIN
BUILDING-Rough-Frame 8/29/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 8/29/2023 Approved AMY COLIN
Green Building Rough 8/29/2023 Not Ready for Inspection AMY COLIN
PLUMBING-Rough 8/29/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 9/7/2023 Approved AMY COLIN
PLUMBING-Rough 9/7/2023 Approved AMY COLIN
Wood Frame 9/7/2023 Conditional Approval AMY COLIN
Insulation 9/13/2023 Not Ready for Inspection AMY COLIN
Interior/Exterior Lathing 9/13/2023 Partial Approval AMY COLIN
PLUMBING-Rough 9/13/2023 Approved AMY COLIN
Insulation 9/22/2023 Approved ROY SPAULDING
Drywall Nailing 9/29/2023 Corrections Issued AMY COLIN
Green Building Rough 9/29/2023 Approved AMY COLIN
Shower Pan 10/27/2023 Approved JOSH MEISTER
Shower Pan 3/6/2024 No Access for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 3/14/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/15/2024 Approved LILIANA PORTILLO
Drywall Nailing 5/15/2024 Approved LILIANA PORTILLO
Final 5/15/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 5/15/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 5/15/2024 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 5/15/2024 Not Ready for Inspection LILIANA PORTILLO
Final 6/10/2024 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 6/10/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/13/2024 Approved LILIANA PORTILLO
Final 6/13/2024 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 6/13/2024 Approved LILIANA PORTILLO
PLUMBING-Final 6/13/2024 Approved LILIANA PORTILLO
Service/Power Release 6/13/2024 Approved LILIANA PORTILLO