14147 W ALBERS PL 91401
Certificate Information: 14147 W ALBERS PL 91401
- Application / Permit
- 21014-20000-04492
- Plan Check / Job No.
- B21VN11975
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 8'-4" X 8" ADDITION TO AND CONVERT THE (E) DETACHED PATIO COVER WITH POOL BATH INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 1/17/2023
- Issuing Office
- Valley
- Current Status
- Issued on 1/17/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2021 | SERGIO MUNIZ |
| Corrections Issued | 9/13/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 10/23/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 12/4/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 3/18/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 4/9/2022 | SERGIO MUNIZ |
| Plan Check Approved | 5/4/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 1/13/2023 | APPLICANT |
| Issued | 1/17/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/5/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/10/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Ross Brothers General Contractors; Lic. No.: 1059195-B | 26933 SEA VISTA DRIVE MALIBU, CA 90265 |
| Engineer | Husain,, Shahzain; Lic. No.: C62744 | 1843 MONTGOMERY RD THOUSAND OAKS, CA 91360 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/13/2023 | Approved | ROBERT GOLD |
| Underground Mechanical | 3/15/2023 | Approved | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 3/17/2023 | Corrections Issued | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/2/2023 | Corrections Issued | ROBERT GOLD |
| ELECTRICAL-Rough | 6/2/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Rough | 6/2/2023 | Approved | ROBERT GOLD |
| HVAC-Rough | 6/2/2023 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 6/2/2023 | Corrections Issued | ROBERT GOLD |
| ELECTRICAL-Rough | 6/8/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 6/8/2023 | Conditional Approval | RYAN SALAZAR |
| PLUMBING-Rough | 6/8/2023 | Approved | RYAN SALAZAR |
| Special/Order Compliance | 6/8/2023 | Corrections Issued | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/16/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/16/2023 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 6/27/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 6/27/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/8/2023 | Approved | RYAN SALAZAR |
| Final | 7/3/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 7/3/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 7/3/2024 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 7/3/2024 | Approved | RYAN SALAZAR |