19933 W WELLS DR 91364
Certificate Information: 19933 W WELLS DR 91364
- Application / Permit
- 21014-20000-04465
- Plan Check / Job No.
- B21VN11905
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) SFD EXCEPT FOR ONE 5'-0" WALL AND BUILD NEW 2-STORY SINGLE FAMILY DWELLING 6102.06 SQFT WITH ATTACHED 3 CAR GARAGE 593 SQFT, (101'-10"x60'-6") W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/5/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | PETER MOSESIAN |
| Corrections Issued | 9/26/2021 | PETER MOSESIAN |
| Quality Review Completed | 9/29/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 10/1/2021 | APPLICANT |
| Applicant returned to address corrections | 3/1/2022 | PETER MOSESIAN |
| Applicant returned to address corrections | 4/4/2022 | PETER MOSESIAN |
| Plan Check Approved | 8/4/2022 | PETER MOSESIAN |
| Issued | 8/5/2022 | APPLICANT |
| CofO in Progress | 2/21/2025 | SEAN WIRCH |
| Permit Finaled | 2/28/2025 | JOHN JANSON |
| CofO Issued | 2/28/2025 | JOHN JANSON |
| Permit Finaled | 2/28/2025 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/23/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 12/23/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 12/23/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 12/23/2021 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 12/23/2021 | DAGOVERTO GUERRERO |
| Watercourse | Cleared | 12/23/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/20/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 3/4/2022 | MARCO SANCHEZ |
| Hydrant and Access approval | Cleared | 3/20/2022 | CINDY JOSSELYN |
| Roof/Waste drainage to street | Cleared | 4/12/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/5/2023 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 6/28/2023 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 7/25/2023 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 7/25/2023 | Corrections Issued | PETER FOLLING |
| Deputy Reinf. Concrete | 7/26/2023 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 7/26/2023 | Partial Approval | PETER FOLLING |
| PLUMBING-Rough | 7/26/2023 | Partial Approval | PETER FOLLING |
| Deputy Reinf. Concrete | 8/8/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 8/8/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 11/9/2023 | Approved | PETER FOLLING |
| Underground Mechanical | 11/14/2023 | Approved | PETER FOLLING |
| Deputy Wood Construction | 11/29/2023 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2023 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/11/2023 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 12/11/2023 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 12/18/2023 | Approved | JOHN KIDWELL |
| HVAC-Rough | 12/19/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/4/2024 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/26/2024 | Approved | JOHN KIDWELL |
| Green Building Rough | 1/26/2024 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 1/26/2024 | Approved | JOHN KIDWELL |
| Insulation | 1/30/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/30/2024 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 2/8/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/15/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 1/3/2025 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Final | 1/3/2025 | Conditional Approval | JOHN KIDWELL |
| Final | 1/27/2025 | Corrections Issued | JOHN HAYES |
| Green Building Final | 1/27/2025 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 1/27/2025 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 2/6/2025 | Approved | SEAN WIRCH |
| Service/Power Release | 2/6/2025 | Approved | SEAN WIRCH |
| Final | 2/24/2025 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 2/24/2025 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 2/24/2025 | SGSOV Approved | SEAN WIRCH |
| Smoke Detectors | 2/24/2025 | Approved | SEAN WIRCH |