15470 W VICTORY BLVD 91406

Certificate Information: 15470 W VICTORY BLVD 91406

Application / Permit
21014-20000-04452
Plan Check / Job No.
B21VN11882
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO DETACHED GARAGE AND CONVERT TO ADU.
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 6/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 JOE VO
Corrections Issued 9/3/2021 JOE VO
Applicant returned to address corrections 9/14/2021 JOE VO
Plan Check Approved 2/18/2022 JOE VO
Issued 3/10/2022 APPLICANT
CofO in Progress 5/28/2024 RYAN SALAZAR
No Progress 6/12/2024 ROBERT GOLD
CofO in Progress 6/12/2024 ROBERT GOLD
Permit Finaled 6/21/2024 RUBEN SALAS
CofO Issued 6/21/2024 RUBEN SALAS
Permit Finaled 6/21/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/7/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 9/7/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/8/2021 GABRIEL ROBLES
Sewer availability Cleared 9/8/2021 GABRIEL ROBLES
Construction near power lines Cleared 2/15/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/14/2023 Partial Approval RYAN SALAZAR
Underground Mechanical 11/14/2023 Approved RYAN SALAZAR
Deputy Drilled-In Anchors 11/17/2023 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 11/21/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 12/13/2023 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 12/13/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval RYAN SALAZAR
Gas Test 12/13/2023 Approved RYAN SALAZAR
PLUMBING-Final 12/13/2023 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 12/13/2023 Approved RYAN SALAZAR
Sewer 12/13/2023 Approved RYAN SALAZAR
Insulation 12/28/2023 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 12/28/2023 Approved RYAN SALAZAR
Shower Pan 12/28/2023 Approved RYAN SALAZAR
Insulation 1/3/2024 Approved RYAN SALAZAR
Drywall Nailing 1/9/2024 Approved RYAN SALAZAR
Special/Order Compliance 1/9/2024 Corrections Issued RYAN SALAZAR
BUILDING-Rough-Frame 4/19/2024 Approved RYAN SALAZAR
Final 4/19/2024 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 4/19/2024 Approved RYAN SALAZAR
Green Building Final 4/19/2024 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 4/19/2024 Approved RYAN SALAZAR
MERV13>=Final 4/19/2024 Approved RYAN SALAZAR
MERV13>=Rough 4/19/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/19/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 4/19/2024 Approved RYAN SALAZAR
Final 5/17/2024 Not Ready for Inspection RYAN SALAZAR
Green Building Final 5/17/2024 Approved RYAN SALAZAR
Final 5/24/2024 OK to Issue CofO RYAN SALAZAR
Service/Power Release 6/5/2024 Approved RYAN SALAZAR