16620 W BIRCHER ST 91344
Certificate Information: 16620 W BIRCHER ST 91344
- Application / Permit
- 21014-20000-04445
- Plan Check / Job No.
- B21VN11859
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACH PATIO TO DEN (27'-7"x13'-10") AND (27'-7x13'-2'-0"), 53 SQFT ADDITION W/NEW ATTACHED UNCOVERED DECK AT REAR., INTERIOR REMODEL TO THE (E) BEDROOM,
- Permit Issued
- Issued on 2/27/2022
- Issuing Office
- Current Status
- CofO Issued on 5/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | PETER MOSESIAN |
| Corrections Issued | 11/12/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 11/16/2021 | APPLICANT |
| Plan Check Approved | 1/24/2022 | PETER MOSESIAN |
| Issued | 2/27/2022 | APPLICANT |
| CofO in Progress | 3/28/2023 | JAVIER RAMOS JR |
| Permit Finaled | 5/2/2023 | MICHAEL SMITH |
| CofO Issued | 5/2/2023 | MICHAEL SMITH |
| Permit Finaled | 5/2/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/19/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2021 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 11/30/2021 | MANUEL TEJADA |
| Construction near power lines | Cleared | 1/19/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/1/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 6/9/2022 | Corrections Issued | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Approved | JAVIER RAMOS JR |
| Deputy Wood Construction | 7/13/2022 | Conditional Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 7/18/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2022 | Approved | JAVIER RAMOS JR |
| Wood Frame | 7/18/2022 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 7/26/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/26/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 8/1/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/1/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 12/30/2022 | Approved | JAVIER RAMOS JR |
| Final | 12/30/2022 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 12/30/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 12/30/2022 | Approved | JAVIER RAMOS JR |
| Final | 3/28/2023 | OK to Issue CofO | JAVIER RAMOS JR |