11448 N HASKELL AVE 91344

Certificate Information: 11448 N HASKELL AVE 91344

Application / Permit
21014-20000-04443
Plan Check / Job No.
B21VN11855
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
13' - 11 1/2" X 27' - 10 1/2" ADDITION OF A DEN AND LAUNDRY ROOM TO THE (E) SFD. ALL WORK PER ENG.
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 PARISA ZAHABI
Corrections Issued 9/2/2021 PARISA ZAHABI
Building Plans Picked Up 9/3/2021 APPLICANT
Issued 11/3/2021 APPLICANT
CofO in Progress 8/22/2023 JENNIFER RABUCHIN
Permit Finaled 4/16/2024 DANIEL ORRANTE
CofO Issued 4/16/2024 DANIEL ORRANTE
Permit Finaled 4/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/22/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/24/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/24/2021 LEE GUILBEAUX
Grading Pre-Inspection Cleared 10/14/2021 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/10/2022 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 5/19/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 5/19/2022 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 8/30/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 9/6/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 9/13/2022 Partial Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 9/20/2022 Approved JENNIFER RABUCHIN
Special/Order Compliance 9/20/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/13/2023 Approved JENNIFER RABUCHIN
Green Building Rough 1/13/2023 Approved JENNIFER RABUCHIN
Insulation 1/13/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 5/19/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/3/2023 Approved JENNIFER RABUCHIN
Final 8/3/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/3/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 8/3/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/3/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/3/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 8/3/2023 Approved JENNIFER RABUCHIN
Final 8/22/2023 OK to Issue CofO JENNIFER RABUCHIN