12510 W BROMWICH ST 91331
Certificate Information: 12510 W BROMWICH ST 91331
- Application / Permit
- 21014-20000-04441
- Plan Check / Job No.
- B21VN11854
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 22' DETACHED GARAGE AND ADD 21'-10" X 25'-5" TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ADD 3'-5" X 5'-6" PORCH. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/7/2022
- Issuing Office
- Current Status
- Issued on 7/7/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/9/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 3/5/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/9/2022 | APPLICANT |
| Issued | 7/7/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/12/2021 | CARLOS AGUILERA |
| ZI | Cleared | 10/12/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/19/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 1/7/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/15/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 2/23/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/24/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/3/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 8/11/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 8/18/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 8/18/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/9/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/9/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 2/9/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 2/9/2023 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/3/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/3/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/3/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/3/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/3/2023 | Approved | MICHEL ABAJAN |
| Insulation | 3/28/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/28/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/11/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 4/11/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/12/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/22/2023 | Approved | MICHEL ABAJAN |
| Final | 12/22/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/22/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/22/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/22/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/22/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 12/22/2023 | Approved | MICHEL ABAJAN |