3138 S PURDUE AVE 90066

Certificate Information: 3138 S PURDUE AVE 90066

Application / Permit
21014-20000-04434
Plan Check / Job No.
B21VN11837
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
151 SQFT ADDITION AND INTERIOR/EXTERIOR REMODEL TO (E) SFD W/ NEW 102 SQFT COVERED PORCH
Permit Issued
Issued on 6/16/2022
Issuing Office
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 PETER MOSESIAN
Corrections Issued 10/5/2021 PETER MOSESIAN
Quality Review Completed 10/13/2021 OMID HEDAYAT
Building Plans Picked Up 10/14/2021 APPLICANT
Plan Check Approved 2/3/2022 PETER MOSESIAN
Issued 6/16/2022 APPLICANT
CofO in Progress 2/22/2024 JESUS PINEDA
Permit Finaled 2/27/2024 DANIEL ORRANTE
CofO Issued 2/27/2024 DANIEL ORRANTE
Permit Finaled 2/27/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/7/2021 HUGO RICO
Eng Process Fee Ord 176,300 Cleared 12/9/2021 HUGO RICO
Grading Pre-Inspection Cleared 2/3/2022 PETER MOSESIAN

Contact Information

Contractor Glynn Designbuild Inc; Lic. No.: 841188-B 1763 TOPANGA SKYLINE DRIVE      TOPANGA, CA 90290
Engineer Simonian,, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/25/2022 Conditional Approval JOHNNY MIRANDA
Footing/Foundation/Slab 7/27/2022 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 8/5/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 8/30/2022 Partial Approval JOHNNY MIRANDA
Green Building Rough 8/30/2022 Not Ready for Inspection JOHNNY MIRANDA
MERV13>=Rough 8/30/2022 Not Ready for Inspection JOHNNY MIRANDA
Deputy Wood Construction 9/1/2022 Conditional Approval JOHNNY MIRANDA
Wood Frame 10/5/2022 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 11/15/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 11/15/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 11/15/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 1/11/2023 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 1/11/2023 Corrections Issued JOHNNY MIRANDA
Shower Pan 1/11/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 2/1/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 2/1/2023 Approved JOHNNY MIRANDA
Insulation 3/24/2023 Approved JOHNNY MIRANDA
Drywall Nailing 4/11/2023 Corrections Issued JOHNNY MIRANDA
Green Building Rough 4/11/2023 Approved JOHNNY MIRANDA
Drywall Nailing 4/17/2023 Conditional Approval RICHARD STEINBACH
Interior/Exterior Lathing 4/17/2023 Partial Approval RICHARD STEINBACH
Gas Test 7/25/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 9/29/2023 Approved ARAM AVEDISIAN
Drywall Nailing 9/29/2023 Approved ARAM AVEDISIAN
Final 9/29/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 9/29/2023 Not Ready for Inspection ARAM AVEDISIAN
MERV13>=Final 9/29/2023 Not Ready for Inspection ARAM AVEDISIAN
MERV13>=Rough 9/29/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 9/29/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 9/29/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 10/23/2023 Approved JESUS PINEDA
Final 10/23/2023 Corrections Issued JESUS PINEDA
Green Building Final 10/23/2023 Approved JESUS PINEDA
HVAC-Final 10/23/2023 Approved JESUS PINEDA
MERV13>=Final 10/23/2023 Approved JESUS PINEDA
Final 2/22/2024 OK to Issue CofO JESUS PINEDA