6115 N GLIDE AVE 91367

Certificate Information: 6115 N GLIDE AVE 91367

Application / Permit
21014-20000-04422
Plan Check / Job No.
B21VN11810
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
31'-9" X 14'-7"ADDITION OF MASTER BATHROOM AND FAMILY ROOM TO (E) SINGLE FAMILY DWELLING. "COMPLY WITH DEPARTMENT ORDER effective date 08/06/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE OTC#924316".
Permit Issued
Issued on 10/4/2021
Issuing Office
Current Status
CofO Issued on 5/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2021 APPLICANT
Assigned to Plan Check Engineer 9/1/2021 SERGIO MUNIZ
Corrections Issued 9/1/2021 SERGIO MUNIZ
Plan Check Approved 9/15/2021 SERGIO MUNIZ
Building Plans Picked Up 9/23/2021 APPLICANT
Issued 10/4/2021 APPLICANT
CofO in Progress 3/10/2023 ROBERT SUNSERI
Permit Finaled 5/21/2023 DAVID JAMES
CofO Issued 5/21/2023 DAVID JAMES
Permit Finaled 5/21/2023 DAVID JAMES

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/8/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 9/8/2021 GABRIEL ROBLES

Contact Information

Contractor Martinez Jose Lucio; Lic. No.: 931506-B 11500 SPROULE AVE      PACOIMA, CA 91331
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/7/2021 Approved RICHARD SIMONS
Deputy Drilled-In Anchors 1/14/2022 Approved RICHARD SIMONS
Excavation/Setback/Form/Re-Bar 1/14/2022 Approved RICHARD SIMONS
Shower Pan 1/31/2022 Corrections Issued RICHARD SIMONS
Wood Frame 1/31/2022 Corrections Issued RICHARD SIMONS
Shower Pan 2/3/2022 Approved RICHARD SIMONS
Wood Frame 2/3/2022 Approved RICHARD SIMONS
Insulation 2/15/2022 Corrections Issued RICHARD SIMONS
Insulation 2/18/2022 Corrections Issued RICHARD SIMONS
Insulation 2/23/2022 Approved RICHARD SIMONS
Drywall Nailing 3/2/2022 Partial Approval RICHARD SIMONS
Interior/Exterior Lathing 3/2/2022 Corrections Issued RICHARD SIMONS
Interior/Exterior Lathing 3/9/2022 Corrections Issued ROBERT SUNSERI
Drywall Nailing 3/16/2022 Approved RICHARD SIMONS
Interior/Exterior Lathing 3/16/2022 Approved RICHARD SIMONS
BUILDING-Rough-Frame 4/8/2022 Corrections Issued RICHARD SIMONS
Final 4/8/2022 Not Ready for Inspection RICHARD SIMONS
Footing/Foundation/Slab 4/8/2022 Approved RICHARD SIMONS
Green Building Final 4/8/2022 Corrections Issued RICHARD SIMONS
Green Building Rough 4/8/2022 Corrections Issued RICHARD SIMONS
SGSOV-Seismic Gas S/O Valve 4/8/2022 SGSOV Not Ready RICHARD SIMONS
Smoke Detectors 4/8/2022 Corrections Issued RICHARD SIMONS
BUILDING-Rough-Frame 4/20/2022 Approved RICHARD SIMONS
Final 4/20/2022 Not Ready for Inspection RICHARD SIMONS
Green Building Final 4/20/2022 Corrections Issued RICHARD SIMONS
Green Building Rough 4/20/2022 Approved RICHARD SIMONS
SGSOV-Seismic Gas S/O Valve 4/20/2022 SGSOV Not Ready RICHARD SIMONS
Smoke Detectors 4/20/2022 Corrections Issued RICHARD SIMONS
Final 4/27/2022 Corrections Issued RICHARD SIMONS
Green Building Final 4/27/2022 Approved RICHARD SIMONS
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Approved RICHARD SIMONS
Smoke Detectors 4/27/2022 Approved RICHARD SIMONS
Final 12/14/2022 No Access for Inspection ROBERT SUNSERI
Final 12/27/2022 Corrections Issued ROBERT SUNSERI
Final 1/27/2023 Corrections Issued ROBERT SUNSERI
Final 2/24/2023 Conditional Approval ROBERT SUNSERI