15442 W CAMARILLO ST 91403

Certificate Information: 15442 W CAMARILLO ST 91403

Application / Permit
21014-20000-04421
Plan Check / Job No.
B21VN11809
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRR. SHAPED 19'-6.25" x 42'-3.5" AT REAR AND 13'-3" x 10'-4.5" AT FRONT ADDITION TO (E) ONE-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND MAJOR REMODEL; NFPA-13D THRU-OUT
Permit Issued
Issued on 1/10/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 SEAN SHAHMIRI
Corrections Issued 10/27/2021 SEAN SHAHMIRI
Quality Review Completed 10/27/2021 OMID HEDAYAT
Building Plans Picked Up 11/1/2021 APPLICANT
Applicant returned to address corrections 1/21/2022 SEAN SHAHMIRI
Plan Check Approved 1/10/2023 SEAN SHAHMIRI
Issued 1/10/2023 APPLICANT
CofO in Progress 2/28/2024 VINCENT HANLEY
CofO Issued 5/30/2024 JOHN JANSON
Permit Finaled 5/30/2024 JOHN JANSON

Permit Application Clearance Information

Trees in Parkway Cleared 9/9/2022 ADALBERTO VERA
Miscellaneous Cleared 12/8/2022 DAGOVERTO GUERRERO
Permit Cleared 12/8/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/9/2022 CARLOS AGUILERA
Sewer availability Cleared 12/9/2022 CARLOS AGUILERA
Low Impact Development Cleared 1/3/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 1/3/2023 COLIN LOREDO

Contact Information

Contractor Right Choice Renovation Inc; Lic. No.: 1066263-B 17000 VENTURA BLVD #302      ENCINO, CA 91316
Engineer Lobana,, Singh Maninder Pa; Lic. No.: C50989 885 PATRIOT DR #G      MOORPARK, CA 93021

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/13/2023 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 1/23/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 1/23/2023 Approved VINCENT HANLEY
Deputy Reinf. Concrete 1/24/2023 Approved VINCENT HANLEY
Insulation 1/31/2023 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 1/31/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 2/23/2023 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Partial Approval VINCENT HANLEY
Green Building Rough 2/23/2023 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 2/23/2023 Not Ready for Inspection VINCENT HANLEY
MERV13>=Rough 2/23/2023 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 2/23/2023 Partial Approval VINCENT HANLEY
Wood Frame 2/23/2023 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/14/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 3/14/2023 Approved VINCENT HANLEY
Green Building Rough 3/14/2023 Approved VINCENT HANLEY
HVAC-Rough 3/14/2023 Approved VINCENT HANLEY
MERV13>=Rough 3/14/2023 Approved VINCENT HANLEY
PLUMBING-Rough 3/14/2023 Approved VINCENT HANLEY
Insulation 3/23/2023 Approved VINCENT HANLEY
Drywall Nailing 3/30/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/30/2023 Approved VINCENT HANLEY
Shower Pan 3/30/2023 Approved VINCENT HANLEY
Final 8/16/2023 Corrections Issued VINCENT HANLEY
Final 10/5/2023 Corrections Issued VINCENT HANLEY
Green Building Final 10/5/2023 Approved VINCENT HANLEY
MERV13>=Final 10/5/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/5/2023 SGSOV Approved VINCENT HANLEY
Smoke Detectors 10/5/2023 Approved VINCENT HANLEY
Service/Power Release 10/11/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 2/27/2024 Approved VINCENT HANLEY
Final 2/27/2024 OK to Issue CofO VINCENT HANLEY
HVAC-Final 2/27/2024 Approved VINCENT HANLEY
PLUMBING-Final 2/27/2024 Approved VINCENT HANLEY