642 N CAHUENGA BLVD 90004
Certificate Information: 642 N CAHUENGA BLVD 90004
- Application / Permit
- 21014-20000-04420
- Plan Check / Job No.
- B21VN11808
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) ATTACHED CARPORT. PROPOSED 23'-4" X 37'-2" IRREGULAR SHAPED ADDITION AND MAJOR REMODEL TO (E) SFD. ALL WORK PER ENGINEERING. NFPA 13D FIRESPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 6/29/2022
- Issuing Office
- Current Status
- CofO Issued on 6/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/27/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 9/30/2021 | STEVEN KIM |
| Building Plans Picked Up | 10/1/2021 | APPLICANT |
| Applicant returned to address corrections | 5/26/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 6/14/2022 | RAPHAEL ROSAS |
| Issued | 6/29/2022 | APPLICANT |
| CofO in Progress | 5/19/2023 | JEFFREY MEAD |
| No Progress | 5/31/2023 | SCOTT FINNILA |
| CofO in Progress | 5/31/2023 | SCOTT FINNILA |
| CofO in Progress | 6/8/2023 | JEFFREY MEAD |
| CofO in Progress | 6/8/2023 | JEFFREY MEAD |
| Permit Finaled | 6/17/2023 | DEROLD HAUFF |
| CofO Issued | 6/17/2023 | DEROLD HAUFF |
| Permit Finaled | 6/17/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2021 | AMAAN MALIK |
| Sewer availability | Cleared | 10/28/2021 | AMAAN MALIK |
| Low Impact Development | Cleared | 3/3/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 3/8/2022 | AMAAN MALIK |
| HPOZ | Cleared | 5/26/2022 | SUKI GERSHENHORN |
| ZI | Cleared | 5/26/2022 | SUKI GERSHENHORN |
Contact Information
| Engineer | Bustillos, Portillo, Alejandro Ivan; Lic. No.: C87257 | 4749 W 169TH STREET LAWNDALE, CA 90260 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 7/27/2022 | Partial Inspection | JULIAN AMAYA |
| Deputy Drilled-In Anchors | 8/2/2022 | No Access for Inspection | JULIAN AMAYA |
| Footing/Foundation/Slab | 8/9/2022 | Approved | JEFFREY MEAD |
| METHANE-Barrier | 8/9/2022 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 8/9/2022 | Approved | JEFFREY MEAD |
| Deputy Reinf. Concrete | 8/15/2022 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 9/22/2022 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Approved | JEFFREY MEAD |
| Sewer | 9/22/2022 | Approved | JEFFREY MEAD |
| Underground Mechanical | 9/22/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/28/2022 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 9/28/2022 | Not Ready for Inspection | JEFFREY MEAD |
| METHANE-Rough | 9/28/2022 | Approved | JEFFREY MEAD |
| Rough-Elec/Plmb/HVAC | 10/6/2022 | Corrections Issued | JEFFREY MEAD |
| Shower Pan | 10/6/2022 | Approved | JEFFREY MEAD |
| Insulation | 10/11/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 10/20/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 11/9/2022 | Approved | MICHAEL LEWIS |
| Green Building Rough | 11/9/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 12/9/2022 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 1/26/2023 | Approved | JEFFREY MEAD |
| Special/Order Compliance | 2/24/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 3/10/2023 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 3/15/2023 | Approved | JEFFREY MEAD |
| Final | 3/15/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 3/15/2023 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 3/15/2023 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 5/11/2023 | Approved | JEFFREY MEAD |
| Final | 5/11/2023 | Partial Approval | JEFFREY MEAD |
| Green Building Final | 5/11/2023 | Approved | JEFFREY MEAD |
| HVAC-Final | 5/11/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 5/11/2023 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 5/11/2023 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 5/11/2023 | Approved | JEFFREY MEAD |
| Smoke Detectors | 5/11/2023 | Approved | JEFFREY MEAD |
| Final | 5/19/2023 | Corrections Issued | JEFFREY MEAD |