1143 W 41ST PL 90037
Certificate Information: 1143 W 41ST PL 90037
- Application / Permit
- 21014-20000-04417
- Plan Check / Job No.
- B21VN11806
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 2ND STORY ACCESSORY DWELLING UNIT ABOVE (E) DETACHED GARAGE PER LAMC 12.22A33(c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/29/2022
- Issuing Office
- Current Status
- Issued on 6/29/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | COLIN LOREDO |
| Corrections Issued | 10/7/2021 | COLIN LOREDO |
| Quality Review Completed | 10/12/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 10/13/2021 | APPLICANT |
| Plan Check Approved | 6/7/2022 | COLIN LOREDO |
| Issued | 6/29/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2021 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 11/13/2021 | ERIK BEASLEY |
| Construction near power lines | Cleared | 1/20/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2022 | THAN WIN |
| Sewer availability | Cleared | 1/27/2022 | THAN WIN |
Contact Information
| Contractor | H L Construction; Lic. No.: 882917-B | 4122 SOUTH BUDLONG AVENUE LOS ANGELES, CA 90037 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/15/2024 | Corrections Issued | CRAIG DAVIS |
| Deputy Wood Construction | 4/17/2025 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 4/30/2025 | Partial Approval | MICHAEL LEWIS |
| Rough-Elec/Plmb/HVAC | 5/2/2025 | Corrections Issued | WAYNE REGESTER |
| Wood Frame | 5/2/2025 | Corrections Issued | WAYNE REGESTER |
| ELECTRICAL-Rough | 6/10/2025 | Not Ready for Inspection | SABAS ALONSO |
| Wood Frame | 6/10/2025 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 6/18/2025 | Partial Approval | ALEX COLIN |
| BUILDING-Rough-Frame | 6/23/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 6/23/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 6/23/2025 | Approved | SABAS ALONSO |
| Insulation | 6/30/2025 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 7/18/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 7/18/2025 | Approved | RONNIE MEDINA |
| Sewer | 10/7/2025 | Approved | MICHAEL LEWIS |