13367 1/2 W BERG ST 91342

Certificate Information: 13367 1/2 W BERG ST 91342

Application / Permit
21014-20000-04416
Plan Check / Job No.
B21VN11805
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 32' x 35'-8" ONE-STORY ACCESSORY DWELLING UNIT TO (E) DET. GARAGE PER LAMC 12.22 A.33 (c)-(d); ALL WORK PER WFPP
Permit Issued
Issued on 4/18/2022
Issuing Office
Current Status
CofO Issued on 11/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2021 APPLICANT
Assigned to Plan Check Engineer 9/30/2021 SEAN SHAHMIRI
Corrections Issued 10/4/2021 SEAN SHAHMIRI
Quality Review Completed 10/12/2021 OMID HEDAYAT
Building Plans Picked Up 10/14/2021 APPLICANT
Applicant returned to address corrections 2/16/2022 SEAN SHAHMIRI
Plan Check Approved 3/1/2022 SEAN SHAHMIRI
Issued 4/18/2022 APPLICANT
CofO in Progress 10/18/2023 KEVIN BERBERYAN
Permit Finaled 11/7/2023 RUBEN SALAS
CofO Issued 11/7/2023 RUBEN SALAS
Permit Finaled 11/7/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/3/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/8/2021 CARLOS AGUILERA
Sewer availability Cleared 11/8/2021 CARLOS AGUILERA
Construction near power lines Cleared 1/28/2022 RIDWAN HARDY
Low Impact Development Cleared 2/8/2022 MARCO SANCHEZ
Grading Pre-Inspection Cleared 2/17/2022 SEAN SHAHMIRI
Roof/Waste drainage to street Cleared 2/22/2022 CARLOS AGUILERA
Public Works-Open Permits Cleared 2/22/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/16/2022 Partial Approval ARAM AVEDISIAN
Sewer 12/16/2022 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 12/28/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 2/22/2023 No Access for Inspection DAVID MATSON
HVAC-Rough 2/22/2023 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 2/22/2023 Not Ready for Inspection DAVID MATSON
Wood Frame 2/22/2023 Corrections Issued DAVID MATSON
BUILDING-Rough-Frame 2/28/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/28/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 2/28/2023 Approved MICHEL ABAJAN
HVAC-Rough 2/28/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 2/28/2023 Approved MICHEL ABAJAN
Insulation 3/8/2023 Conditional Approval ARAM AVEDISIAN
Interior/Exterior Lathing 3/8/2023 Approved ARAM AVEDISIAN
Shower Pan 3/8/2023 Approved ARAM AVEDISIAN
Drywall Nailing 3/22/2023 Approved ARAM AVEDISIAN
Insulation 3/22/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 9/21/2023 Not Ready for Inspection KEVIN BERBERYAN
Final 9/21/2023 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/21/2023 Approved KEVIN BERBERYAN
HVAC-Final 9/21/2023 Approved KEVIN BERBERYAN
PLUMBING-Final 9/21/2023 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/21/2023 Approved KEVIN BERBERYAN
ELECTRICAL-Final 10/2/2023 Approved KEVIN BERBERYAN
Final 10/2/2023 Conditional Approval KEVIN BERBERYAN
HVAC-Final 10/2/2023 Approved KEVIN BERBERYAN
PLUMBING-Final 10/2/2023 Approved KEVIN BERBERYAN
Service/Power Release 10/2/2023 Corrections Issued KEVIN BERBERYAN
Service/Power Release 10/12/2023 Approved KEVIN BERBERYAN
Final 10/18/2023 OK to Issue CofO KEVIN BERBERYAN