11057-11059 N BURNET AVE 91345
Certificate Information: 11057-11059 N BURNET AVE 91345
- Application / Permit
- 21014-20000-04384
- Plan Check / Job No.
- B21VN11718
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 18'-0" x 18'-0" ATTACHED GARAGE INTO A (N) JR. ADU PER GCS 65852.2(e)(1)(A) AND GCS 65852.22 AND ADD (N) 18'-0" x 12'-0" ATTACHED PATIO COVER. ALL WORK TO COMPLY WITH WFPP. SEE COMMENTS. "COMPLY WITH DEPARTMENT ORDER effective date 11/12/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | ALFRED RAMIREZ |
| Corrections Issued | 9/2/2021 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 10/27/2021 | ALFRED RAMIREZ |
| Issued | 11/2/2021 | APPLICANT |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| CofO in Progress | 7/28/2022 | LEO MILBAUER |
| CofO Issued | 8/30/2022 | DAVID JAMES |
| Permit Finaled | 8/30/2022 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 9/21/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/21/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/28/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/4/2022 | Not Ready for Inspection | EMIL ALEXANDRIAN |
| Reinforced Concrete Frame | 2/4/2022 | Approved | EMIL ALEXANDRIAN |
| Underground Mechanical | 2/4/2022 | Approved | EMIL ALEXANDRIAN |
| ELECTRICAL-Rough | 2/15/2022 | Approved | JASON BRANNON |
| Gas Test | 2/15/2022 | Approved | JASON BRANNON |
| HVAC-Rough | 2/15/2022 | Approved | JASON BRANNON |
| PLUMBING-Rough | 2/15/2022 | Approved | JASON BRANNON |
| Wood Frame | 2/15/2022 | Approved | JASON BRANNON |
| ELECTRICAL-Rough | 2/17/2022 | Approved | JASON BRANNON |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Approved | JASON BRANNON |
| Gas Test | 2/17/2022 | Not Ready for Inspection | JASON BRANNON |
| HVAC-Rough | 2/17/2022 | Approved | JASON BRANNON |
| PLUMBING-Rough | 2/17/2022 | Approved | JASON BRANNON |
| Wood Frame | 2/17/2022 | Approved | JASON BRANNON |
| Insulation | 2/23/2022 | Approved | JASON BRANNON |
| Interior/Exterior Lathing | 2/23/2022 | Approved | JASON BRANNON |
| Drywall Nailing | 3/1/2022 | Approved | JASON BRANNON |
| Green Building Rough | 3/1/2022 | Approved | JASON BRANNON |
| Interior/Exterior Lathing | 3/1/2022 | Approved | JASON BRANNON |
| Shower Pan | 3/1/2022 | Approved | JASON BRANNON |
| BUILDING-Rough-Frame | 4/20/2022 | Approved | JASON BRANNON |
| Final | 4/20/2022 | No Access for Inspection | JASON BRANNON |
| Footing/Foundation/Slab | 4/20/2022 | Approved | JASON BRANNON |
| Green Building Final | 4/20/2022 | No Access for Inspection | JASON BRANNON |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Not Ready | JASON BRANNON |
| Smoke Detectors | 4/20/2022 | No Access for Inspection | JASON BRANNON |
| Final | 5/12/2022 | Conditional Approval | JASON BRANNON |
| Green Building Final | 5/12/2022 | Approved | JASON BRANNON |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Approved | JASON BRANNON |
| Smoke Detectors | 5/12/2022 | Approved | JASON BRANNON |