17012 W ESCALON DR 91436
Certificate Information: 17012 W ESCALON DR 91436
- Application / Permit
- 21014-20000-04379
- Plan Check / Job No.
- B21VN11691
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL INT. AND EXT. WALLS EXCEPT FOR 1'-4" SIDE WALL AND ERECT A 77'-2" x 57'-6" TWO-STORY SINGLE FAMILY DWELLING ROOF DECK, ATT. 2-CAR GARAGE AND ATT. OPEN TRELLIS; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | SEAN SHAHMIRI |
| Corrections Issued | 9/27/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 9/27/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/30/2021 | APPLICANT |
| Applicant returned to address corrections | 6/21/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 8/10/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 9/13/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 9/21/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 9/26/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 10/6/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 10/18/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 11/3/2022 | SEAN SHAHMIRI |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 1/28/2025 | SEAN WIRCH |
| CofO Issued | 2/3/2025 | JOHN JANSON |
| Permit Finaled | 2/3/2025 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/13/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 10/13/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 10/13/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 10/13/2021 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Permit | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Watercourse | Cleared | 10/13/2021 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 12/21/2021 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 5/5/2022 | GREGORY HOERNER |
| Low Impact Development | Cleared | 5/26/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 6/9/2022 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 8/5/2022 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Markov,, George P; Lic. No.: C55855 | 1623 THOMPSON AVE GLENDALE, CA 91201 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/6/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 5/17/2023 | Partial Approval | VINCENT HANLEY |
| Sewer | 5/17/2023 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/26/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 5/30/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Steel/Welding | 7/7/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Partial Approval | VINCENT HANLEY |
| Special/Order Compliance | 8/8/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/11/2023 | Corrections Issued | VINCENT HANLEY |
| Deputy Wood Construction | 9/11/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 9/19/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/5/2023 | Approved | VINCENT HANLEY |
| HVAC-Rough | 10/5/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/11/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 10/11/2023 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 10/11/2023 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 10/11/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/17/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Shower Pan | 10/17/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/30/2023 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 10/30/2023 | Not Ready for Inspection | SEAN HAUPT |
| Insulation | 10/30/2023 | Corrections Issued | SEAN HAUPT |
| Verify Sprinkler Sign Off | 10/30/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 11/1/2023 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/7/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/15/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 11/15/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | Approved | VINCENT HANLEY |
| Green Building Rough | 11/15/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/17/2024 | Approved | JEFFREY BULL |
| Service/Power Release | 5/17/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Final | 6/20/2024 | Approved | SEAN WIRCH |
| HVAC-Final | 6/20/2024 | Approved | SEAN WIRCH |
| PLUMBING-Final | 6/20/2024 | Approved | SEAN WIRCH |
| Final | 8/16/2024 | Partial Inspection | SEAN WIRCH |
| Footing/Foundation/Slab | 8/16/2024 | Approved | SEAN WIRCH |
| Green Building Final | 8/16/2024 | Partial Inspection | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV Not Ready | SEAN WIRCH |
| Smoke Detectors | 8/16/2024 | Approved | SEAN WIRCH |
| Final | 1/29/2025 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 1/29/2025 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | SEAN WIRCH |