6236 N FARMDALE AVE 91606

Certificate Information: 6236 N FARMDALE AVE 91606

Application / Permit
21014-20000-04346
Plan Check / Job No.
B21VN11617
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 2 BEDRMS & 2 BATHRMS ADDN (15'10"X29'4") BETWEEN EX SFD & DET GARAGE TO CREATE A SFD W/ ATT GARAGE. REDUCE SIZE OF EX BEDRM TO CREATE A HALLWAY TO THE ADDN PER PLAN.
Permit Issued
Issued on 6/22/2023
Issuing Office
Current Status
CofO Issued on 7/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2021 APPLICANT
Assigned to Plan Check Engineer 9/3/2021 HAYATO TSUCHIYA
Corrections Issued 9/4/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 4/28/2022 HAYATO TSUCHIYA
Building Plans Picked Up 5/4/2022 APPLICANT
Applicant returned to address corrections 9/7/2022 SERGIO MUNIZ
Plan Check Approved 1/10/2023 ALFRED RAMIREZ
Issued 6/22/2023 APPLICANT
CofO in Progress 6/27/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 7/23/2024 RUBEN SALAS
CofO Issued 7/23/2024 RUBEN SALAS
Permit Finaled 7/23/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/8/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 9/13/2022 MEGAN GODINEZ
Sewer availability Cleared 9/13/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 9/13/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 9/13/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 9/13/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/2/2023 Corrections Issued ROBERT GOLD
Footing/Foundation/Slab 8/2/2023 Not Ready for Inspection ROBERT GOLD
PLUMBING-Rough 8/2/2023 Corrections Issued ROBERT GOLD
Excavation/Setback/Form/Re-Bar 8/7/2023 Not Ready for Inspection JOHN HAYES
Underground Mechanical 8/7/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/14/2023 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 8/14/2023 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/18/2023 Approved JOHN HAYES
PLUMBING-Rough 8/18/2023 Partial Approval JOHN HAYES
PLUMBING-Rough 9/11/2023 Partial Approval JOHN HAYES
Gas Test 9/18/2023 Approved JOHN HAYES
PLUMBING-Rough 9/18/2023 Partial Approval JOHN HAYES
Insulation 9/22/2023 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/29/2023 Corrections Issued JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 12/6/2023 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 12/6/2023 Approved JOHN COLEMAN
Green Building Rough 12/6/2023 Approved JOHN COLEMAN
HVAC-Rough 12/6/2023 Not Ready for Inspection JOHN COLEMAN
Insulation 12/6/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 12/6/2023 Approved JOHN COLEMAN
HVAC-Rough 12/11/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 12/11/2023 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 1/17/2024 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 1/17/2024 Partial Approval JOHN HAYES
Shower Pan 1/17/2024 Approved JOHN HAYES
Insulation 1/19/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 1/19/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Drywall Nailing 1/25/2024 Approved JOHN HAYES
Interior/Exterior Lathing 1/25/2024 Approved JOHN HAYES
BUILDING-Rough-Frame 3/6/2024 Not Ready for Inspection THOMAS FINNILA
Final 3/6/2024 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 3/6/2024 Not Ready for Inspection THOMAS FINNILA
Green Building Final 3/6/2024 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 3/6/2024 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 3/6/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 5/13/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/13/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 5/13/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/13/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/13/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 6/3/2024 Approved ROBERTO PALACIOS-LOPEZ
Gas Test 6/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 6/3/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 6/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 6/3/2024 Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 6/3/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 6/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 6/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 6/14/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 6/20/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 6/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Final 6/27/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Gas Test 6/27/2024 Approved ROBERTO PALACIOS-LOPEZ