17351 W ENADIA WAY 91406
Certificate Information: 17351 W ENADIA WAY 91406
- Application / Permit
- 21014-20000-04330
- Plan Check / Job No.
- B21VN11558
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (14'-8"x4'-0") 50 SQFT ADDITION AT FRONT AND (4'-9"x6'-8") 30 SQFT ADDITION AT REAR AND REMODEL SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 11/5/2021
- Issuing Office
- Current Status
- CofO Issued on 2/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2021 | PETER MOSESIAN |
| Corrections Issued | 8/30/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 9/2/2021 | APPLICANT |
| Plan Check Approved | 9/28/2021 | PETER MOSESIAN |
| Issued | 11/5/2021 | APPLICANT |
| CofO in Progress | 1/5/2023 | SEAN HAUPT |
| Permit Finaled | 2/2/2023 | JOHN JANSON |
| CofO Issued | 2/2/2023 | JOHN JANSON |
| Permit Finaled | 2/2/2023 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/15/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Franceschi,, Paul; Lic. No.: S4309 | 2388 KENILWORTH AVE LOS ANGELES, CA 90039 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/30/2022 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 3/31/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 3/31/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 5/9/2022 | Conditional Approval | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 5/12/2022 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 5/26/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 5/26/2022 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 5/26/2022 | Approved | SEAN HAUPT |
| Insulation | 6/2/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 6/24/2022 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 6/24/2022 | Partial Approval | ROBERT GOLD |
| Gas Test | 7/21/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/21/2022 | Approved | JUSTIN HAWLEY |
| Final | 12/15/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 12/15/2022 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 12/15/2022 | Approved | SEAN HAUPT |
| Final | 1/4/2023 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 1/4/2023 | Approved | SEAN HAUPT |