6059 N TEESDALE AVE 91606
Certificate Information: 6059 N TEESDALE AVE 91606
- Application / Permit
- 21014-20000-04313
- Plan Check / Job No.
- B21VN11502
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 23' X 5'- 3 7/8" ADDITION TO THE (E) DETACHED GARAGE AND CONVERT GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g). ALL WORK PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 05/18/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 2/7/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | OMAR GARNICA |
| Corrections Issued | 9/7/2021 | OMAR GARNICA |
| Applicant returned to address corrections | 1/25/2022 | OMAR GARNICA |
| Plan Check Approved | 1/27/2022 | OMAR GARNICA |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| Issued | 2/7/2022 | APPLICANT |
| CofO in Progress | 8/22/2024 | SCOTT SHUSTER |
| Permit Finaled | 10/10/2024 | DAVID JAMES |
| CofO Issued | 10/10/2024 | DAVID JAMES |
| Permit Finaled | 10/10/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 1/5/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 1/7/2022 | RIDWAN HARDY |
| Sewer availability | Cleared | 1/14/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/5/2022 | Not Ready for Inspection | BRYAN MEYER |
| PLUMBING-Rough | 4/5/2022 | Not Ready for Inspection | BRYAN MEYER |
| Pre-Inspection | 4/5/2022 | Approved | BRYAN MEYER |
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Corrections Issued | BRYAN MEYER |
| Rough-Elec/Plmb/HVAC | 6/27/2022 | Corrections Issued | BRYAN MEYER |
| Underground Mechanical | 8/3/2022 | Partial Approval | BRYAN MEYER |
| Excavation/Setback/Form/Re-Bar | 8/9/2022 | Not Ready for Inspection | BRYAN MEYER |
| Footing/Foundation/Slab | 8/9/2022 | Not Ready for Inspection | BRYAN MEYER |
| Excavation/Setback/Form/Re-Bar | 8/12/2022 | Approved | BRYAN MEYER |
| Footing/Foundation/Slab | 8/12/2022 | Approved | BRYAN MEYER |
| Special/Order Compliance | 8/12/2022 | Approved | BRYAN MEYER |
| BUILDING-Rough-Frame | 8/24/2023 | Not Ready for Inspection | BRYAN MEYER |
| ELECTRICAL-Rough | 8/24/2023 | Not Ready for Inspection | BRYAN MEYER |
| Green Building Rough | 8/24/2023 | Not Ready for Inspection | BRYAN MEYER |
| HVAC-Rough | 8/24/2023 | Not Ready for Inspection | BRYAN MEYER |
| PLUMBING-Rough | 8/24/2023 | Not Ready for Inspection | BRYAN MEYER |
| Wood Frame | 8/24/2023 | Not Ready for Inspection | BRYAN MEYER |
| ELECTRICAL-Rough | 9/11/2023 | Not Ready for Inspection | BRYAN MEYER |
| HVAC-Rough | 9/11/2023 | Not Ready for Inspection | BRYAN MEYER |
| PLUMBING-Rough | 9/11/2023 | Not Ready for Inspection | BRYAN MEYER |
| PLUMBING-Rough | 4/25/2024 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 5/14/2024 | Partial Inspection | SCOTT SHUSTER |
| ELECTRICAL-Rough | 5/14/2024 | Partial Inspection | SCOTT SHUSTER |
| HVAC-Rough | 5/14/2024 | Partial Inspection | SCOTT SHUSTER |
| PLUMBING-Rough | 5/14/2024 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 5/21/2024 | Partial Inspection | SCOTT SHUSTER |
| Deputy Drilled-In Anchors | 5/21/2024 | Conditional Approval | SCOTT SHUSTER |
| ELECTRICAL-Rough | 5/21/2024 | Approved | SCOTT SHUSTER |
| Final | 5/21/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| Green Building Final | 5/21/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| Green Building Rough | 5/21/2024 | Approved | SCOTT SHUSTER |
| HVAC-Rough | 5/21/2024 | Partial Inspection | SCOTT SHUSTER |
| PLUMBING-Rough | 5/21/2024 | Partial Inspection | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Not Ready | SCOTT SHUSTER |
| Smoke Detectors | 5/21/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| HVAC-Final | 5/23/2024 | Approved | SCOTT SHUSTER |
| PLUMBING-Final | 5/23/2024 | Approved | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 5/30/2024 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 7/30/2024 | Approved | SCOTT SHUSTER |
| Final | 7/30/2024 | Partial Inspection | SCOTT SHUSTER |
| Green Building Final | 7/30/2024 | Approved | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Approved | SCOTT SHUSTER |
| Smoke Detectors | 7/30/2024 | Approved | SCOTT SHUSTER |
| Final | 8/16/2024 | Partial Approval | JOSE RUBIO |
| Final | 8/22/2024 | OK to Issue CofO | SCOTT SHUSTER |