22743 W BERDON ST 91367
Certificate Information: 22743 W BERDON ST 91367
- Application / Permit
- 21014-20000-04306
- Plan Check / Job No.
- B21VN11480
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 30' X 35' IRREGULAR SHAPED AND REMODEL (E) SFD. NFPA 13D FIRE SPRINKLERS REQUIRED. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/13/2022
- Issuing Office
- Current Status
- CofO Issued on 3/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/2/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/1/2021 | RAPHAEL ROSAS |
| Issued | 1/13/2022 | APPLICANT |
| Building Plans Picked Up | 1/14/2022 | APPLICANT |
| CofO in Progress | 6/29/2022 | TROY SANDERS |
| Permit Finaled | 3/11/2023 | DANIEL ORRANTE |
| CofO Issued | 3/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/5/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 10/13/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/8/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 11/15/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 12/1/2021 | RAPHAEL ROSAS |
| GPI Written Notices | Cleared | 1/13/2022 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/1/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/10/2022 | Partial Approval | TROY SANDERS |
| Green Building Rough | 2/10/2022 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 2/10/2022 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 3/1/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 3/8/2022 | Not Ready for Inspection | TROY SANDERS |
| Final | 3/8/2022 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 3/8/2022 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 3/8/2022 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Not Ready | TROY SANDERS |
| Smoke Detectors | 3/8/2022 | Not Ready for Inspection | TROY SANDERS |
| Verify Sprinkler Sign Off | 3/8/2022 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 3/29/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 3/29/2022 | Approved | TROY SANDERS |
| Green Building Rough | 3/29/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 3/29/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 4/7/2022 | Approved | JESUS PINEDA |
| Final | 6/6/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 6/6/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 6/6/2022 | Approved | TROY SANDERS |
| Final | 6/28/2022 | OK to Issue CofO | TROY SANDERS |