11162 N RESEDA BLVD 91326
Certificate Information: 11162 N RESEDA BLVD 91326
- Application / Permit
- 21014-20000-04304
- Plan Check / Job No.
- B21VN11476
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION OF 2ND FLR AND 1ST FLOOR TO (E) 1 STORY SFD ; FIRE SPRINKLER NFPA 13D
- Permit Issued
- Issued on 4/6/2022
- Issuing Office
- Current Status
- Issued on 4/6/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 9/28/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 10/7/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 1/24/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 3/14/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 4/6/2022 | MOHAMMAD ESMAILI |
| Issued | 4/6/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 12/2/2021 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 12/8/2021 | VASIL MIHALEV |
| Low Impact Development | Cleared | 2/22/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 2/22/2022 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 4/6/2022 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mani,, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/5/2022 | Conditional Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 5/11/2022 | Partial Approval | JEFFREY PARD |
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 5/25/2022 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 6/1/2022 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 6/1/2022 | Not Ready for Inspection | JEFFREY PARD |
| MERV13>=Rough | 6/1/2022 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 6/23/2022 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 6/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| MERV13>=Rough | 6/23/2022 | Not Ready for Inspection | JEFFREY PARD |
| Reinforced Concrete Frame | 6/23/2022 | Approved | JEFFREY PARD |
| Wood Frame | 6/23/2022 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 8/29/2022 | Corrections Issued | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2022 | Not Ready for Inspection | JEFFREY PARD |
| Gas Test | 8/29/2022 | Approved | JEFFREY PARD |
| HVAC-Rough | 8/29/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 8/29/2022 | Corrections Issued | JEFFREY PARD |
| Wood Frame | 8/29/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 9/6/2022 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 9/6/2022 | Not Ready for Inspection | SEAN WIRCH |
| Service/Power Release | 9/6/2022 | Not Ready for Inspection | SEAN WIRCH |
| Wood Frame | 9/6/2022 | Corrections Issued | SEAN WIRCH |
| PLUMBING-Rough | 9/14/2022 | Corrections Issued | DAVID SANDOVAL |
| Service/Power Release | 9/14/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Wood Frame | 9/14/2022 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 9/21/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 9/28/2022 | Partial Approval | KRISTEN CAUSEY |
| Shower Pan | 9/28/2022 | Partial Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 9/29/2022 | Partial Inspection | MORRIS JACKSON |
| Shower Pan | 9/29/2022 | Approved | MORRIS JACKSON |
| Insulation | 10/5/2022 | Conditional Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 10/5/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 11/7/2022 | Approved | DAVID SCANTLIN |
| Insulation | 11/7/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/14/2024 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Final | 3/14/2024 | Approved | KRISTEN CAUSEY |
| Final | 3/14/2024 | Corrections Issued | KRISTEN CAUSEY |
| Green Building Final | 3/14/2024 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 3/14/2024 | Approved | KRISTEN CAUSEY |
| HVAC-Final | 3/14/2024 | Approved | KRISTEN CAUSEY |
| MERV13>=Final | 3/14/2024 | Approved | KRISTEN CAUSEY |
| MERV13>=Rough | 3/14/2024 | Approved | KRISTEN CAUSEY |
| PLUMBING-Final | 3/14/2024 | Approved | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Approved | KRISTEN CAUSEY |
| Smoke Detectors | 3/14/2024 | Approved | KRISTEN CAUSEY |