6159 N AUCKLAND AVE 91606
Certificate Information: 6159 N AUCKLAND AVE 91606
- Application / Permit
- 21014-20000-04282
- Plan Check / Job No.
- B21VN11421
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 6/13/2022
- Issuing Office
- Current Status
- CofO Issued on 6/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | LAMAR DAVIS |
| Corrections Issued | 10/13/2021 | LAMAR DAVIS |
| Quality Review Completed | 10/18/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/6/2022 | LAMAR DAVIS |
| Plan Check Approved | 5/16/2022 | LAMAR DAVIS |
| Issued | 6/13/2022 | APPLICANT |
| CofO in Progress | 5/28/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 6/27/2023 | MICHAEL SMITH |
| CofO Issued | 6/27/2023 | MICHAEL SMITH |
| Permit Finaled | 6/27/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/18/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/18/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/25/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 3/15/2022 | SUNG JOON WON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mani,, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/5/2022 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 7/14/2022 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 7/21/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 7/21/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 8/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 8/10/2022 | Partial Approval | JOHN HAYES |
| Verify Sprinkler Sign Off | 8/10/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/15/2022 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 8/15/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 9/16/2022 | Partial Approval | JOHN HAYES |
| Green Building Rough | 9/16/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 9/16/2022 | Partial Approval | JOHN HAYES |
| Verify Sprinkler Sign Off | 9/16/2022 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Not Ready for Inspection | ALAN MORELOS |
| Rough-Elec/Plmb/HVAC | 9/23/2022 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 9/23/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/7/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 10/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 10/7/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 10/7/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 10/7/2022 | Approved | JOHN HAYES |
| Wood Frame | 10/7/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 10/17/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 10/28/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 11/10/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 11/10/2022 | Partial Approval | JOHN HAYES |
| Insulation | 11/23/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 12/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 12/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 12/6/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 12/23/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 3/31/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Drywall Nailing | 3/31/2023 | Approved | DAVID ANDERSON |
| Final | 3/31/2023 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 3/31/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 3/31/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 3/31/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 3/31/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 4/7/2023 | Approved | JENNIFER RABUCHIN |
| Final | 4/7/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 4/7/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 4/7/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/26/2023 | Approved | JENNIFER RABUCHIN |
| Final | 5/26/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 5/26/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/26/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 5/26/2023 | Approved | JENNIFER RABUCHIN |