7323 N NITA AVE 91303

Certificate Information: 7323 N NITA AVE 91303

Application / Permit
21014-20000-04281
Plan Check / Job No.
B21VN11413
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 9'7-1/2" X 9'5" LAUNDRY RM ADDITION AT REAR. REMOVE WALL BETWEEN DINING AREA & KITCHEN AND REMODEL KITCHEN. NEW PANTRY & CLOSET PER PLAN.
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
CofO Issued on 12/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 HAYATO TSUCHIYA
Corrections Issued 9/2/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 10/10/2021 HAYATO TSUCHIYA
Plan Check Approved 10/22/2021 HAYATO TSUCHIYA
Building Plans Picked Up 10/27/2021 APPLICANT
Issued 11/4/2021 APPLICANT
CofO in Progress 12/9/2022 CHRIS CHRISTENSEN
Permit Finaled 12/20/2022 JOHN JANSON
CofO Issued 12/20/2022 JOHN JANSON
Permit Finaled 12/20/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/5/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 10/5/2021 GABRIEL ROBLES

Contact Information

Contractor Treeium Inc; Lic. No.: 617148-B 5352 LAUREL CANYON BLVD #200      VALLEY VILLAGE, CA 91607
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/25/2022 Approved JEFFREY PARD
Footing/Foundation/Slab 2/25/2022 Approved JEFFREY PARD
PLUMBING-Rough 2/25/2022 Partial Approval JEFFREY PARD
Pre-Inspection 4/26/2022 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 5/4/2022 Approved JESUS PINEDA
Deputy Wood Construction 5/4/2022 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 5/5/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/26/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/26/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 5/26/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 5/26/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/26/2022 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 5/26/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/20/2022 Approved JEFFREY PARD
Green Building Rough 6/20/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 6/23/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/23/2022 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 6/23/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/20/2022 Approved JUSTIN HAWLEY
Green Building Rough 7/26/2022 Approved CHRIS CHRISTENSEN
Insulation 7/26/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 7/29/2022 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Not Ready CHRIS CHRISTENSEN
ELECTRICAL-Final 10/5/2022 Approved CHRIS CHRISTENSEN
Final 10/5/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/5/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 10/5/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/5/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/5/2022 Approved CHRIS CHRISTENSEN
Final 10/28/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/28/2022 Corrections Issued CHRIS CHRISTENSEN
Final 12/8/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 12/8/2022 Approved CHRIS CHRISTENSEN