7323 N NITA AVE 91303
Certificate Information: 7323 N NITA AVE 91303
- Application / Permit
- 21014-20000-04281
- Plan Check / Job No.
- B21VN11413
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 9'7-1/2" X 9'5" LAUNDRY RM ADDITION AT REAR. REMOVE WALL BETWEEN DINING AREA & KITCHEN AND REMODEL KITCHEN. NEW PANTRY & CLOSET PER PLAN.
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- CofO Issued on 12/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 9/2/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 10/10/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/22/2021 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 10/27/2021 | APPLICANT |
| Issued | 11/4/2021 | APPLICANT |
| CofO in Progress | 12/9/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 12/20/2022 | JOHN JANSON |
| CofO Issued | 12/20/2022 | JOHN JANSON |
| Permit Finaled | 12/20/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 10/5/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Treeium Inc; Lic. No.: 617148-B | 5352 LAUREL CANYON BLVD #200 VALLEY VILLAGE, CA 91607 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/25/2022 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 2/25/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 2/25/2022 | Partial Approval | JEFFREY PARD |
| Pre-Inspection | 4/26/2022 | Approved | CHRIS CHRISTENSEN |
| Deputy Drilled-In Anchors | 5/4/2022 | Approved | JESUS PINEDA |
| Deputy Wood Construction | 5/4/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 5/5/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/26/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 5/26/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 5/26/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 5/26/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/26/2022 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 5/26/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/20/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 6/20/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 6/23/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/23/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/23/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/20/2022 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 7/26/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 7/26/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 7/29/2022 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 10/5/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 10/5/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 10/5/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 10/5/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 10/5/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 10/5/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 10/28/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 10/28/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 12/8/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 12/8/2022 | Approved | CHRIS CHRISTENSEN |