6347 W 79TH ST 90045
Certificate Information: 6347 W 79TH ST 90045
- Application / Permit
- 21014-20000-04276
- Plan Check / Job No.
- B21VN11377
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY IRREGULAR SHAPED ADDITION TO (E) 1-STORY SFD W/ ATTACHED GARAGE CONSISTING OF CONVERTING (E) GARAGE INTO LIVING ROOM, ADD (N) 2-CAR GARAGE, EXPAND (E) FAMILYROOM/DINING ROOM, ADD (N) LIBRARY & TRELLIS ON 1ST FLOOR & ADD (4) BEDROOMS, (3) FULL BATHROOMS & DECK ON 2ND FLOOR; MAJOR REMODEL (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 11/24/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Building Plans Picked Up | 9/22/2020 | APPLICANT |
| Submitted | 8/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/14/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 9/16/2021 | STEVEN KIM |
| Applicant returned to address corrections | 11/3/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 11/10/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 11/15/2021 | NILOOFAR MEHRAIN |
| Issued | 11/24/2021 | APPLICANT |
| CofO in Progress | 7/28/2022 | HERBERT GIRON |
| Permit Finaled | 8/2/2022 | DANIEL ORRANTE |
| CofO Issued | 8/2/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/2/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/12/2021 | LONDY ALVARADO |
| Hydrant and Access approval | Cleared | 10/21/2021 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 10/21/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/22/2021 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 10/25/2021 | KEVIN ARUCAN |
| GPI Written Notices | Cleared | 11/15/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 11/15/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/20/2021 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 1/7/2022 | Conditional Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 1/7/2022 | Conditional Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 1/7/2022 | Partial Approval | JOHN KAYON |
| PLUMBING-Rough | 1/14/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2022 | Approved | JOHN KAYON |
| Wood Frame | 1/28/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Corrections Issued | CLAYTON GRAHAM |
| Deputy Wood Construction | 2/10/2022 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/10/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 3/10/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 3/10/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/10/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/11/2022 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 3/11/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/11/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/15/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 3/15/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 3/15/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/18/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 3/18/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/18/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 3/18/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/22/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 3/31/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/31/2022 | Approved | JESUS RODRIGUEZ |
| Sewer | 5/13/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 5/13/2022 | Approved | JESUS RODRIGUEZ |
| Gas Test | 7/21/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 7/21/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 7/21/2022 | Corrections Issued | HERBERT GIRON |
| Service/Power Release | 7/21/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/25/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 7/25/2022 | Corrections Issued | ANDREW NAVE |
| Final | 7/25/2022 | Corrections Issued | ANDREW NAVE |
| Green Building Final | 7/25/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 7/25/2022 | Approved | ANDREW NAVE |
| PLUMBING-Final | 7/25/2022 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Approved | ANDREW NAVE |
| Service/Power Release | 7/25/2022 | Approved | ANDREW NAVE |
| Smoke Detectors | 7/25/2022 | Not Ready for Inspection | ANDREW NAVE |
| ELECTRICAL-Final | 7/27/2022 | Approved | HERBERT GIRON |
| Final | 7/27/2022 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 7/27/2022 | Approved | HERBERT GIRON |
| Smoke Detectors | 7/27/2022 | Approved | HERBERT GIRON |