7718 N BAKMAN AVE 91352
Certificate Information: 7718 N BAKMAN AVE 91352
- Application / Permit
- 21014-20000-04272
- Plan Check / Job No.
- B21VN11367
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-3" X 12'-6" REAR ADDITION TO THE (E) SFD AND REMODELING THE CLOSET IN THE BEDROOM. ALL WORK PER WFPP. SEE COMMENT.
- Permit Issued
- Issued on 11/16/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2021 | PARISA ZAHABI |
| Corrections Issued | 9/8/2021 | PARISA ZAHABI |
| Issued | 11/16/2021 | APPLICANT |
| Building Plans Picked Up | 11/18/2021 | APPLICANT |
| CofO in Progress | 3/1/2023 | MATTHEW NELSON |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
| CofO Issued | 3/4/2023 | MICHAEL SMITH |
| Permit Finaled | 3/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/2/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 1/25/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/4/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 2/8/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| FLOOD-Proofing Certificate | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 4/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/6/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 2/22/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 2/22/2023 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 2/22/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 2/22/2023 | Approved | MATTHEW NELSON |
| Final | 2/28/2023 | OK to Issue CofO | MATTHEW NELSON |