9040 N GOTHIC AVE 91343
Certificate Information: 9040 N GOTHIC AVE 91343
- Application / Permit
- 21014-20000-04267
- Plan Check / Job No.
- B21VN11350
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 20' X 12' ADDITION TO DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 10/6/2021
- Issuing Office
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 8/31/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 10/4/2021 | GURUNATH NESARAJAH |
| Issued | 10/6/2021 | APPLICANT |
| Building Plans Picked Up | 10/12/2021 | APPLICANT |
| CofO in Progress | 1/10/2023 | RAUL OLAGI |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
| CofO Issued | 1/21/2023 | MICHAEL SMITH |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 9/15/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/16/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2021 | No Access for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 11/8/2021 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 11/12/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/12/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/27/2021 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 12/27/2021 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Rough | 12/27/2021 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 12/27/2021 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/13/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 1/13/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 1/13/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 1/13/2022 | Corrections Issued | RAUL OLAGI |
| Shower Pan | 1/13/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 1/28/2022 | Not Ready for Inspection | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 1/28/2022 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 1/28/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 1/28/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/14/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 2/14/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 2/14/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 2/14/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 2/14/2022 | Approved | RAUL OLAGI |
| Insulation | 2/24/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 3/1/2022 | Approved | ALAN MORELOS |
| Sewer | 10/13/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 10/13/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 11/16/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 1/4/2023 | Approved | RAUL OLAGI |
| Final | 1/4/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 1/4/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 1/4/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 1/4/2023 | Approved | RAUL OLAGI |
| Final | 1/10/2023 | OK to Issue CofO | RAUL OLAGI |