1638 W 60TH PL 90047

Certificate Information: 1638 W 60TH PL 90047

Application / Permit
21014-20000-04266
Plan Check / Job No.
B21VN11346
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 10'-5" x 14'-11.5" ADDITION TO THE (E) SINGLE FAMILY DWELLING AT REAR FOR A NEW BEDROOM AND INTERIOR REMODEL.
Permit Issued
Issued on 12/9/2021
Issuing Office
Current Status
CofO Issued on 2/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 SARKIS HARABEDIAN
Corrections Issued 9/15/2021 SARKIS HARABEDIAN
Quality Review Completed 9/16/2021 STEVEN KIM
Applicant returned to address corrections 10/18/2021 SARKIS HARABEDIAN
Plan Check Approved 11/8/2021 SARKIS HARABEDIAN
Building Plans Picked Up 11/8/2021 APPLICANT
Issued 12/9/2021 APPLICANT
CofO in Progress 5/24/2022 ENRIQUE MIRELES
CofO in Progress 5/25/2022 ENRIQUE MIRELES
Permit Finaled 2/18/2023 DANIEL ORRANTE
CofO Issued 2/18/2023 DANIEL ORRANTE
Permit Finaled 2/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/23/2021 CELINA MORENO
Sewer availability Cleared 9/23/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 9/24/2021 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/11/2022 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 1/31/2022 Partial Inspection FREDDIE RIVERA
Insulation 1/31/2022 Partial Inspection FREDDIE RIVERA
Deputy Drilled-In Anchors 2/22/2022 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 2/23/2022 Approved FREDDIE RIVERA
Footing/Foundation/Slab 2/23/2022 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 3/11/2022 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 3/11/2022 Not Ready for Inspection FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 3/11/2022 Partial Approval FREDDIE RIVERA
BUILDING-Rough-Frame 3/16/2022 Approved ENRIQUE MIRELES
Green Building Rough 3/16/2022 Approved ENRIQUE MIRELES
HVAC-Rough 3/16/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/16/2022 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/16/2022 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 3/16/2022 Approved ENRIQUE MIRELES
Insulation 3/21/2022 Approved ENRIQUE MIRELES
Drywall Nailing 3/30/2022 Approved HORACE FULTZ
Final 5/13/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 5/13/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/13/2022 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 5/13/2022 Approved ENRIQUE MIRELES
Smoke Detectors 5/13/2022 Approved ENRIQUE MIRELES
Final 5/20/2022 OK to Issue CofO ENRIQUE MIRELES