19401 1/2 W HEMMINGWAY ST 91335
Certificate Information: 19401 1/2 W HEMMINGWAY ST 91335
- Application / Permit
- 21014-20000-04264
- Plan Check / Job No.
- B21VN11340
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN ADDITION AND CONVERSION TO (E) DETACHED GARAGE TO CREATE A NEW DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Current Status
- CofO in Progress on 4/25/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2021 | CARLOS MONTES |
| Corrections Issued | 8/24/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 8/2/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/24/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 9/4/2023 | MICHAEL LOPEZ |
| Issued | 9/8/2023 | APPLICANT |
| CofO in Progress | 4/2/2025 | ARUTYUN MADATYAN |
| No Progress | 4/25/2026 | MICHAEL PELHAM |
| CofO in Progress | 4/25/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/26/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 6/10/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/17/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/17/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | C B D Construction; Lic. No.: 552681-B | 26500 AGOURA ROAD BOX 848 CALABASAS, CA 91302 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/25/2023 | Partial Approval | JEFFREY BULL |
| Special/Order Compliance | 11/21/2023 | Corrections Issued | JEFFREY BULL |
| Pre-Inspection | 4/11/2024 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 5/15/2024 | Partial Approval | JEFFREY BULL |
| Underground Mechanical | 5/21/2024 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Approved | JEFFREY BULL |
| Special/Order Compliance | 9/16/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 11/22/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Green Building Rough | 11/22/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 11/22/2024 | Partial Approval | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 11/22/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 12/26/2024 | Approved | ARUTYUN MADATYAN |
| Final | 12/26/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 12/26/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Final | 12/26/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/26/2024 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 12/26/2024 | Approved | ARUTYUN MADATYAN |
| Final | 1/31/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 1/31/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 4/2/2025 | Approved | ARUTYUN MADATYAN |
| Final | 4/2/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 4/2/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 4/2/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 4/2/2025 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 4/2/2025 | Approved | ARUTYUN MADATYAN |
| Special/Order Compliance | 5/2/2025 | Corrections Issued | ARUTYUN MADATYAN |