8617-8619 W JAYSEEL ST 91040
Certificate Information: 8617-8619 W JAYSEEL ST 91040
- Application / Permit
- 21014-20000-04262
- Plan Check / Job No.
- B21VN11336
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *ePLAN CHECK* (E) SINGLE FAMILY DWELLING W/ATT GARAGE, CONVERSION OF UNDERFLOOR AREA (520 SQ FT) FOR (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | LAMAR DAVIS |
| Corrections Issued | 10/13/2021 | LAMAR DAVIS |
| Quality Review Completed | 10/18/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/24/2021 | LAMAR DAVIS |
| Plan Check Approved | 11/29/2021 | LAMAR DAVIS |
| Issued | 12/3/2021 | APPLICANT |
| CofO in Progress | 10/21/2022 | MATTHEW NELSON |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Street Frontage | Cleared | 10/20/2021 | CARLOS AGUILERA |
| ZA Case | Cleared | 10/20/2021 | LAUREN PADICK |
| Address approval | Cleared | 10/22/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/22/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/25/2021 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 11/29/2021 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/7/2022 | Corrections Issued | MATTHEW NELSON |
| Pre-Inspection | 1/28/2022 | Partial Inspection | MATTHEW NELSON |
| Underground Mechanical | 2/10/2022 | Partial Approval | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 2/15/2022 | Conditional Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 2/17/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 2/23/2022 | Approved | MATTHEW NELSON |
| Pre-Inspection | 3/11/2022 | Partial Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/25/2022 | Approved | MATTHEW NELSON |
| Pre-Inspection | 4/12/2022 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/22/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/22/2022 | Approved | MATTHEW NELSON |
| Insulation | 7/7/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/7/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 7/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 7/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/26/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/11/2022 | Approved | MATTHEW NELSON |
| Final | 10/11/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 10/11/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 10/11/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 10/11/2022 | Approved | MATTHEW NELSON |
| Final | 10/21/2022 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 10/21/2022 | Approved | MATTHEW NELSON |