115-117 N MCCADDEN PL 90004

Certificate Information: 115-117 N MCCADDEN PL 90004

Application / Permit
21014-20000-04255
Plan Check / Job No.
B21VN11311
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 30' 5" X 19' 3" CARPORT AND 15' 1" X 9' 3" IRR.-SHAPE PORTION OF (E) SFD STORAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 12/17/2021
Issuing Office
West Los Angeles
Current Status
Issued on 12/17/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/20/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 GURUNATH NESARAJAH
Corrections Issued 9/12/2021 GURUNATH NESARAJAH
Quality Review Completed 9/13/2021 OMID HEDAYAT
Building Plans Picked Up 11/18/2021 APPLICANT
Plan Check Approved 12/15/2021 GURUNATH NESARAJAH
Issued 12/17/2021 APPLICANT

Permit Application Clearance Information

CPC Cleared 9/23/2021 RUBEN VASQUEZ
ZI Cleared 9/23/2021 RUBEN VASQUEZ
Address approval Cleared 9/24/2021 WALLIE JONG
HPOZ Cleared 9/24/2021 SUKI GERSHENHORN
Roof/Waste drainage to street Cleared 9/24/2021 WALLIE JONG
Sewer availability Cleared 9/24/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/28/2021 WALLIE JONG

Contact Information

Contractor Plumbing By Todd R Marsh Inc; Lic. No.: 536475-C36 5951 VENICE BLVD      LOS ANGELES, CA 90034

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/25/2022 Approved JOSEPH MCGARRY
PLUMBING-Rough 5/25/2022 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 8/11/2022 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/11/2022 Approved JOSEPH MCGARRY
Gas Test 8/11/2022 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 8/11/2022 Approved JOSEPH MCGARRY
METHANE-Rough 8/11/2022 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 8/11/2022 Partial Approval JOSEPH MCGARRY
Wood Frame 8/11/2022 Partial Approval JOSEPH MCGARRY
Insulation 9/2/2022 Approved MICHAEL LEWIS
Interior/Exterior Lathing 9/2/2022 Approved MICHAEL LEWIS
Shower Pan 9/2/2022 Approved MICHAEL LEWIS
Drywall Nailing 9/13/2022 Approved MICHAEL LEWIS
Gas Test 9/14/2022 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 9/14/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 10/11/2022 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 1/31/2025 Not Ready for Inspection RONNIE MINDANAO
Final 1/31/2025 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 1/31/2025 Not Ready for Inspection RONNIE MINDANAO
Green Building Final 1/31/2025 Not Ready for Inspection RONNIE MINDANAO
METHANE-Barrier 1/31/2025 Not Ready for Inspection RONNIE MINDANAO
METHANE-Subgrade 1/31/2025 Not Ready for Inspection RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 1/31/2025 SGSOV Not Ready RONNIE MINDANAO
Smoke Detectors 1/31/2025 Not Ready for Inspection RONNIE MINDANAO
BUILDING-Rough-Frame 5/15/2026 Approved RONNIE MINDANAO
Final 5/15/2026 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 5/15/2026 Partial Approval RONNIE MINDANAO
Green Building Final 5/15/2026 Approved RONNIE MINDANAO
METHANE-Barrier 5/15/2026 Approved RONNIE MINDANAO
METHANE-Subgrade 5/15/2026 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 5/15/2026 SGSOV Approved RONNIE MINDANAO
Smoke Detectors 5/15/2026 Approved RONNIE MINDANAO
Final 5/29/2026 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 5/29/2026 Approved RONNIE MINDANAO
Final 6/4/2026 Corrections Issued RONNIE MINDANAO
Final 6/8/2026 Corrections Issued RONNIE MINDANAO
Final 6/15/2026 Partial Approval RONNIE MINDANAO