3200 S BARRY AVE 90066
Certificate Information: 3200 S BARRY AVE 90066
- Application / Permit
- 21014-20000-04254
- Plan Check / Job No.
- B21VN11310
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 56'-9" X 29'-9" SECOND FLOOR ADDITION AND FIRST FLOOR REMODEL TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 2/15/2022
- Issuing Office
- Current Status
- CofO Issued on 11/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | SELLA BENYAMIN |
| Corrections Issued | 9/28/2021 | SELLA BENYAMIN |
| Quality Review Completed | 10/8/2021 | STEVEN KIM |
| Building Plans Picked Up | 10/12/2021 | APPLICANT |
| Applicant returned to address corrections | 11/17/2021 | SELLA BENYAMIN |
| Plan Check Approved | 11/30/2021 | SELLA BENYAMIN |
| Issued | 2/15/2022 | APPLICANT |
| CofO in Progress | 11/17/2023 | MICHAEL PELHAM |
| Permit Finaled | 11/18/2023 | DANIEL ORRANTE |
| CofO Issued | 11/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/4/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2021 | DINAH GARIN |
| Sewer availability | Cleared | 11/5/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 11/18/2021 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 11/18/2021 | SELLA BENYAMIN |
Contact Information
| Contractor | Zepeda General Building; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/30/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 7/18/2022 | Conditional Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 8/23/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/9/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 9/9/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/9/2022 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/23/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 9/23/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/23/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/29/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/29/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/29/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 9/29/2022 | Approved | JOHNNY MIRANDA |
| Wood Frame | 9/29/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 10/7/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 10/19/2022 | Conditional Approval | HERBERT GIRON |
| Interior/Exterior Lathing | 10/19/2022 | Conditional Approval | HERBERT GIRON |
| Insulation | 10/25/2022 | Conditional Approval | ANDREW NAVE |
| Drywall Nailing | 11/2/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 11/21/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 11/29/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 11/29/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 12/6/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/23/2022 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 12/27/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 12/27/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/27/2022 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/5/2023 | Approved | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 3/31/2023 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 4/11/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 4/11/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 4/11/2023 | Approved | JOHNNY MIRANDA |
| Final | 4/13/2023 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 4/13/2023 | Approved | JOHNNY MIRANDA |
| Gas Test | 4/13/2023 | Approved | JOHNNY MIRANDA |
| Green Building Final | 4/13/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 4/13/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 4/13/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 4/13/2023 | Approved | JOHNNY MIRANDA |
| Final | 4/18/2023 | Corrections Issued | JOHNNY MIRANDA |
| Final | 11/17/2023 | OK to Issue CofO | MICHAEL PELHAM |