20241-20243 W LASSEN ST 91311

Certificate Information: 20241-20243 W LASSEN ST 91311

Application / Permit
21014-20000-04244
Plan Check / Job No.
B21VN11263
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. CONVERT EXISTING ATACHED GARAGE WITH ADDITION PER ORDINANCE
Permit Issued
Issued on 1/31/2022
Issuing Office
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2021 APPLICANT
Assigned to Plan Check Engineer 8/24/2021 MONICA RAMIREZ
Corrections Issued 8/25/2021 MONICA RAMIREZ
Applicant returned to address corrections 11/30/2021 MONICA RAMIREZ
Plan Check Approved 12/21/2021 MONICA RAMIREZ
Issued 1/31/2022 APPLICANT
CofO in Progress 8/13/2022 JEFFREY PARD
Permit Finaled 8/26/2022 JOHN JANSON
CofO Issued 8/26/2022 JOHN JANSON
Permit Finaled 8/26/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/18/2021 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 11/18/2021 JOSE DUARTE-DIAZ
Watercourse Cleared 11/18/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/20/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/20/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/4/2022 Partial Approval JEFFREY PARD
Excavation/Setback/Form/Re-Bar 3/9/2022 Approved JEFFREY PARD
Footing/Foundation/Slab 3/9/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/1/2022 Partial Approval DAVID SCANTLIN
HVAC-Rough 4/14/2022 Approved JEFFREY PARD
PLUMBING-Rough 4/14/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 4/19/2022 Approved JEFFREY PARD
ELECTRICAL-Rough 4/19/2022 Approved JEFFREY PARD
Green Building Rough 4/19/2022 Not Ready for Inspection JEFFREY PARD
Green Building Rough 4/26/2022 Approved JUSTIN HAWLEY
Insulation 4/26/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 4/26/2022 Approved JUSTIN HAWLEY
Shower Pan 4/26/2022 Approved JUSTIN HAWLEY
Drywall Nailing 4/29/2022 Approved JEFFREY PARD
Final 7/25/2022 No Access for Inspection JEFFREY PARD
Green Building Final 7/25/2022 No Access for Inspection JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Not Ready JEFFREY PARD
Smoke Detectors 7/25/2022 No Access for Inspection JEFFREY PARD
Final 7/29/2022 Corrections Issued JEFFREY PARD
Final 8/4/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 8/4/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 8/4/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 8/4/2022 Approved JEFFREY PARD