ADD & EXPAND (39'-6"x 10'-2") IRR SHAPE M. BED ROOM & BATH/CLOSET AND (39'-1"x 8'-1") FAMILY ROOM & REMODEL TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. WORK PER ENGINEER.
Permit Issued
Issued on 1/27/2022
Issuing Office
Current Status
CofO Issued on 2/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/20/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 TROY DEGUZMAN
Corrections Issued 9/28/2021 TROY DEGUZMAN
Quality Review Completed 10/7/2021 OMID HEDAYAT
Building Plans Picked Up 10/12/2021 APPLICANT
Plan Check Approved 1/27/2022 TROY DEGUZMAN
Issued 1/27/2022 APPLICANT
CofO in Progress 1/22/2024 VINCENT HANLEY
CofO Issued 2/16/2024 JOHN JANSON
Permit Finaled 2/16/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/13/2021 GABRIEL ROBLES
Sewer availability Cleared 10/13/2021 GABRIEL ROBLES
Low Impact Development Cleared 11/17/2021 KHAING AYE
Roof/Waste drainage to street Cleared 11/22/2021 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 1/8/2022 JOHN CONNEALLY
Green Code Cleared 1/25/2022 TROY DEGUZMAN
GPI Written Notices Cleared 1/27/2022 ALEXANDER ANDREWS
Grading Pre-Inspection Cleared 1/27/2022 ALEXANDER ANDREWS

Contact Information

Contractor Owner-Builder       ,
Engineer Khansa,, Eyass Wafik; Lic. No.: C91758 2252 JOSIE AVE      LONG BEACH, CA 90815

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2022 Approved DAVID SANDOVAL
Deputy Drilled-In Anchors 2/15/2022 Conditional Approval JUSTIN HAWLEY
Footing/Foundation/Slab 2/28/2022 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 3/23/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 3/23/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 3/29/2022 Partial Approval DAVID SANDOVAL
Deputy Wood Construction 6/14/2022 Conditional Approval KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 6/22/2022 Partial Approval VINCENT HANLEY
Wood Frame 6/22/2022 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 8/22/2022 No Access for Inspection DAVID SANDOVAL
Service/Power Release 9/13/2022 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 9/20/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 9/20/2022 Approved VINCENT HANLEY
Green Building Rough 9/20/2022 Approved VINCENT HANLEY
HVAC-Rough 9/20/2022 Approved VINCENT HANLEY
MERV13>=Rough 9/20/2022 Approved VINCENT HANLEY
PLUMBING-Rough 9/20/2022 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 9/20/2022 Approved VINCENT HANLEY
Wood Frame 9/20/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Approved JESUS PINEDA
Insulation 10/19/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 10/19/2022 Partial Approval JESUS PINEDA
Shower Pan 10/19/2022 Approved JESUS PINEDA
Drywall Nailing 11/18/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/18/2022 Approved VINCENT HANLEY
Final 1/17/2024 Corrections Issued VINCENT HANLEY
Green Building Final 1/17/2024 Approved VINCENT HANLEY
MERV13>=Final 1/17/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/17/2024 SGSOV Not Ready VINCENT HANLEY
Smoke Detectors 1/17/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 1/19/2024 Approved VINCENT HANLEY
Final 1/19/2024 OK to Issue CofO VINCENT HANLEY
HVAC-Final 1/19/2024 Approved VINCENT HANLEY
PLUMBING-Final 1/19/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/19/2024 SGSOV Approved VINCENT HANLEY