6603 N FIRMAMENT AVE 91406
Certificate Information: 6603 N FIRMAMENT AVE 91406
- Application / Permit
- 21014-20000-04215
- Plan Check / Job No.
- B21VN11167
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 19' X 28' IRREGULAR SHAPED 2-STORY ADDITION TO (E) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/15/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | RAPHAEL ROSAS |
| Corrections Issued | 9/21/2021 | RAPHAEL ROSAS |
| Quality Review Completed | 9/30/2021 | STEVEN KIM |
| Plan Check Approved | 2/7/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 2/9/2022 | APPLICANT |
| Issued | 2/15/2022 | APPLICANT |
| CofO in Progress | 10/31/2022 | RICHARD DOCKUS |
| Permit Finaled | 4/1/2023 | DANIEL ORRANTE |
| CofO Issued | 4/1/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/1/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 10/25/2021 | LAUREN PADICK |
| Sewer availability | Cleared | 10/26/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2021 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 1/12/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 1/12/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 1/29/2022 | JOHN CONNEALLY |
Contact Information
| Contractor | Pavlovich Construction Co; Lic. No.: 388868-B | 22817 VENTURA BLVD 1001 WOODLAND HILLS, CA 91364 |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/1/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Not Ready for Inspection | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2022 | Corrections Issued | ALAN MORELOS |
| Underground Mechanical | 4/6/2022 | Partial Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 5/5/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Partial Approval | RICHARD DOCKUS |
| Gas Test | 5/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 5/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 5/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 5/20/2022 | Partial Approval | JENNIFER RABUCHIN |
| Gas Test | 5/24/2022 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 5/24/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 5/24/2022 | Approved | RICHARD DOCKUS |
| Sewer | 5/24/2022 | Approved | RICHARD DOCKUS |
| Deputy Wood Construction | 6/6/2022 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 6/15/2022 | Partial Approval | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Insulation | 6/22/2022 | Corrections Issued | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/22/2022 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 6/28/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 6/28/2022 | Approved | RICHARD DOCKUS |
| Insulation | 6/28/2022 | Approved | RICHARD DOCKUS |
| MERV13>=Rough | 6/28/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 7/5/2022 | Approved | ASHLEY THOMPSON |
| Final | 9/23/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 9/23/2022 | Approved | RICHARD DOCKUS |
| MERV13>=Final | 9/23/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 9/23/2022 | Approved | RICHARD DOCKUS |
| Final | 10/4/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 10/4/2022 | SGSOV Approved | RICHARD DOCKUS |
| Service/Power Release | 10/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 10/26/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 10/28/2022 | OK to Issue CofO | RICHARD DOCKUS |