14019 W LA MAIDA ST 91423

Certificate Information: 14019 W LA MAIDA ST 91423

Application / Permit
21014-20000-04213
Plan Check / Job No.
B21VN11159
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) SINGLE FAMILY DWELLING EXCEPT FOR WEST SIDE WALL AND BUILD NEW 2 STORY (47'-11"x40'-0"), 2480 SQFT SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE (361 SQFT) AND OPEN TRELLIS W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/11/2022
Issuing Office
Current Status
CofO Issued on 12/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 PETER MOSESIAN
Corrections Issued 9/19/2021 PETER MOSESIAN
Quality Review Completed 9/28/2021 OMID HEDAYAT
Building Plans Picked Up 9/29/2021 APPLICANT
Plan Check Approved 3/9/2022 PETER MOSESIAN
Issued 3/11/2022 APPLICANT
CofO in Progress 11/6/2023 MISAEL ESPARZA
Permit Finaled 12/27/2023 RUBEN SALAS
Permit Finaled 12/27/2023 RUBEN SALAS
CofO Issued 12/27/2023 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development Cleared 10/22/2021 NICK RAYGOZA
Roof/Waste drainage to street Cleared 11/2/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/4/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 11/4/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 1/29/2022 RUEL COLE
ZI Cleared 2/10/2022 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/25/2022 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 5/31/2022 Conditional Approval MISAEL ESPARZA
BUILDING-Rough-Frame 6/17/2022 Corrections Issued MISAEL ESPARZA
Green Building Rough 6/17/2022 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 6/17/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 6/23/2022 Partial Approval CALEB MEISTER
Wood Frame 6/27/2022 Partial Approval JACK KARGODORIAN
Insulation 6/30/2022 Partial Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/11/2022 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 10/20/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 10/20/2022 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 10/20/2022 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 10/27/2022 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 10/27/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 10/27/2022 Approved MISAEL ESPARZA
Green Building Rough 10/27/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 10/27/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 10/27/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/18/2022 Approved MISAEL ESPARZA
Green Building Rough 11/18/2022 Not Ready for Inspection MISAEL ESPARZA
Insulation 2/6/2023 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 2/6/2023 Partial Approval MISAEL ESPARZA
Insulation 2/9/2023 Approved MISAEL ESPARZA
Drywall Nailing 2/15/2023 Approved MISAEL ESPARZA
Green Building Rough 2/15/2023 Approved MISAEL ESPARZA
Shower Pan 2/15/2023 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 4/6/2023 No Access for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 4/13/2023 Approved MICHEL ABAJAN
Green Building Final 7/31/2023 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 7/31/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 8/18/2023 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 10/2/2023 Corrections Issued MISAEL ESPARZA
HVAC-Final 10/2/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 10/2/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 10/5/2023 Not Ready for Inspection MISAEL ESPARZA
Enclosure/Fence 10/5/2023 Partial Inspection MISAEL ESPARZA
HVAC-Final 10/5/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 10/5/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 10/17/2023 Approved MISAEL ESPARZA
HVAC-Final 10/17/2023 Approved MISAEL ESPARZA
PLUMBING-Final 10/17/2023 Approved MISAEL ESPARZA
Service/Power Release 10/26/2023 Approved JUAN VALENZUELA
Final 11/3/2023 OK to Issue CofO MISAEL ESPARZA
Footing/Foundation/Slab 11/3/2023 Approved MISAEL ESPARZA
Green Building Final 11/3/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 11/3/2023 Approved MISAEL ESPARZA