14019 W LA MAIDA ST 91423
Certificate Information: 14019 W LA MAIDA ST 91423
- Application / Permit
- 21014-20000-04213
- Plan Check / Job No.
- B21VN11159
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) SINGLE FAMILY DWELLING EXCEPT FOR WEST SIDE WALL AND BUILD NEW 2 STORY (47'-11"x40'-0"), 2480 SQFT SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE (361 SQFT) AND OPEN TRELLIS W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/11/2022
- Issuing Office
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | PETER MOSESIAN |
| Corrections Issued | 9/19/2021 | PETER MOSESIAN |
| Quality Review Completed | 9/28/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/29/2021 | APPLICANT |
| Plan Check Approved | 3/9/2022 | PETER MOSESIAN |
| Issued | 3/11/2022 | APPLICANT |
| CofO in Progress | 11/6/2023 | MISAEL ESPARZA |
| Permit Finaled | 12/27/2023 | RUBEN SALAS |
| Permit Finaled | 12/27/2023 | RUBEN SALAS |
| CofO Issued | 12/27/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/22/2021 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 11/2/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 11/4/2021 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 1/29/2022 | RUEL COLE |
| ZI | Cleared | 2/10/2022 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 5/31/2022 | Conditional Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/17/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 6/17/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 6/17/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 6/23/2022 | Partial Approval | CALEB MEISTER |
| Wood Frame | 6/27/2022 | Partial Approval | JACK KARGODORIAN |
| Insulation | 6/30/2022 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2022 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/20/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 10/20/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 10/20/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/27/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Wood Construction | 10/27/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/27/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 10/27/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 10/27/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/27/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/18/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 11/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 2/6/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/6/2023 | Partial Approval | MISAEL ESPARZA |
| Insulation | 2/9/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 2/15/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 2/15/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 2/15/2023 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/6/2023 | No Access for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/13/2023 | Approved | MICHEL ABAJAN |
| Green Building Final | 7/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 7/31/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/18/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/2/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 10/2/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 10/2/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/5/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Enclosure/Fence | 10/5/2023 | Partial Inspection | MISAEL ESPARZA |
| HVAC-Final | 10/5/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 10/5/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/17/2023 | Approved | MISAEL ESPARZA |
| HVAC-Final | 10/17/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 10/17/2023 | Approved | MISAEL ESPARZA |
| Service/Power Release | 10/26/2023 | Approved | JUAN VALENZUELA |
| Final | 11/3/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Footing/Foundation/Slab | 11/3/2023 | Approved | MISAEL ESPARZA |
| Green Building Final | 11/3/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 11/3/2023 | Approved | MISAEL ESPARZA |