15277 W COBALT ST 91342

Certificate Information: 15277 W COBALT ST 91342

Application / Permit
21014-20000-04212
Plan Check / Job No.
B21VN11155
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO THE (E) SFD.
Permit Issued
Issued on 6/26/2024
Issuing Office
Valley
Current Status
Issued on 6/26/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/18/2021 APPLICANT
Assigned to Plan Check Engineer 8/27/2021 ARTIN ZARUKIAN
Corrections Issued 8/31/2021 ARTIN ZARUKIAN
Building Plans Picked Up 8/31/2021 APPLICANT
Applicant returned to address corrections 12/12/2023 SERGIO MUNIZ
Plan Check Approved 12/20/2023 SERGIO MUNIZ
Issued 6/26/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/15/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/15/2021 DAGOVERTO GUERRERO
Tract Map conditions Cleared 9/22/2021 PABLO ESTRADA
Low Impact Development Cleared 9/8/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 9/9/2023 JOHN LIN
Tract Map conditions Cleared 12/10/2023 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Jennifer Arianna; Lic. No.: C79156 3828 EARLE AVE      ROSEMEAD, CA 91770

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/27/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 7/29/2024 Partial Approval KEVIN BERBERYAN
Footing/Foundation/Slab 7/29/2024 Partial Approval KEVIN BERBERYAN
Deputy Drilled-In Anchors 10/31/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 11/1/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 11/1/2024 Partial Approval KEVIN BERBERYAN
Insulation 11/8/2024 Not Ready for Inspection KEVIN BERBERYAN
Wood Frame 11/8/2024 Partial Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Partial Approval KEVIN BERBERYAN
ELECTRICAL-Rough 3/6/2025 Corrections Issued KEVIN BERBERYAN
Gas Test 3/6/2025 Approved KEVIN BERBERYAN
HVAC-Rough 3/6/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 3/6/2025 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 3/25/2025 Approved KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 3/25/2025 Approved KEVIN BERBERYAN
Service/Power Release 3/25/2025 Approved KEVIN BERBERYAN
Insulation 4/1/2025 Approved KEVIN BERBERYAN
Drywall Nailing 4/4/2025 Approved KEVIN BERBERYAN
Green Building Rough 4/4/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 3/31/2026 Approved KEVIN BERBERYAN
Final 3/31/2026 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 3/31/2026 Approved KEVIN BERBERYAN
Green Building Final 3/31/2026 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 3/31/2026 Approved KEVIN BERBERYAN