16448 W TULSA ST 91344
Certificate Information: 16448 W TULSA ST 91344
- Application / Permit
- 21014-20000-04209
- Plan Check / Job No.
- B21VN11145
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 15' X 49'2" ADDITION TO ADD BATHROOM, PATIO COVER, AND DEN TO THE (E) SFD PER ENGNIEER.
- Permit Issued
- Issued on 2/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | PINANK PATEL |
| Corrections Issued | 9/3/2021 | PINANK PATEL |
| Applicant returned to address corrections | 1/7/2022 | PINANK PATEL |
| Applicant returned to address corrections | 1/21/2022 | PINANK PATEL |
| Plan Check Approved | 2/2/2022 | PINANK PATEL |
| Issued | 2/2/2022 | APPLICANT |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| CofO in Progress | 11/3/2022 | JAVIER RAMOS JR |
| Permit Finaled | 11/3/2022 | MICHAEL SMITH |
| CofO Issued | 11/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 9/30/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 12/10/2021 | CHRIS PARK |
| Roof/Waste drainage to street | Cleared | 1/13/2022 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/17/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 3/17/2022 | Corrections Issued | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2022 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 4/19/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/29/2022 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/29/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 4/29/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 4/29/2022 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/29/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/5/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/5/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/5/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 5/5/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 5/10/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 5/17/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/17/2022 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 5/27/2022 | Partial Approval | JAVIER RAMOS JR |
| Gas Test | 5/27/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Sewer | 5/27/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 6/6/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/14/2022 | Corrections Issued | DEANDRE HOFFMAN |
| HVAC-Final | 7/14/2022 | Corrections Issued | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 7/21/2022 | Approved | JAVIER RAMOS JR |
| Final | 7/21/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 7/21/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 7/21/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/29/2022 | Approved | JAVIER RAMOS JR |
| Final | 7/29/2022 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/29/2022 | Approved | JAVIER RAMOS JR |
| Gas Test | 7/29/2022 | Approved | JAVIER RAMOS JR |
| Green Building Final | 7/29/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 7/29/2022 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/29/2022 | Approved | JAVIER RAMOS JR |