16943 W COVELLO ST 91406
Certificate Information: 16943 W COVELLO ST 91406
- Application / Permit
- 21014-20000-04203
- Plan Check / Job No.
- B21VN11127
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 19' 11" X 15' 5" TO (E) DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 8/29/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/5/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/11/2022 | GURUNATH NESARAJAH |
| Issued | 3/16/2022 | APPLICANT |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| CofO in Progress | 10/13/2022 | RAUL OLAGI |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/31/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/27/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 2/4/2022 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/14/2022 | Conditional Approval | DEANDRE HOFFMAN |
| PLUMBING-Rough | 4/19/2022 | Partial Approval | ALAN MORELOS |
| Sewer | 4/19/2022 | Approved | ALAN MORELOS |
| Footing/Foundation/Slab | 4/21/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 4/25/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/10/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Rough | 5/10/2022 | Not Ready for Inspection | RAUL OLAGI |
| Deputy Wood Construction | 5/11/2022 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 5/31/2022 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/22/2022 | Partial Approval | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 6/22/2022 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 6/22/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| HVAC-Rough | 6/22/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 6/22/2022 | Partial Approval | DEANDRE HOFFMAN |
| PLUMBING-Rough | 6/22/2022 | Corrections Issued | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 6/28/2022 | Approved | ALAN MORELOS |
| Gas Test | 6/28/2022 | Approved | ALAN MORELOS |
| Green Building Rough | 6/28/2022 | Approved | ALAN MORELOS |
| Insulation | 6/28/2022 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 6/28/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 6/28/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 7/5/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 9/21/2022 | Corrections Issued | ALAN MORELOS |
| Final | 9/21/2022 | Corrections Issued | ALAN MORELOS |
| Green Building Final | 9/21/2022 | Approved | ALAN MORELOS |
| HVAC-Final | 9/21/2022 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Final | 9/21/2022 | Corrections Issued | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Not Ready | ALAN MORELOS |
| Smoke Detectors | 9/21/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 9/26/2022 | Corrections Issued | RAUL OLAGI |
| Final | 9/26/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 9/26/2022 | Approved | RAUL OLAGI |
| PLUMBING-Final | 9/26/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 10/12/2022 | Approved | RAUL OLAGI |
| Final | 10/12/2022 | OK to Issue CofO | RAUL OLAGI |
| PLUMBING-Final | 10/12/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 10/12/2022 | SGSOV Approved | RAUL OLAGI |