5946 N WHITE OAK AVE 91316
Certificate Information: 5946 N WHITE OAK AVE 91316
- Application / Permit
- 21014-20000-04202
- Plan Check / Job No.
- B21VN11125
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19' 6" X 30' MASTER BEDROOM/BATHROOM/CLOSET/LAUNDRY ADDITION TO REAR AND REMODEL (E) KITCHEN. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- CofO Issued on 1/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 8/28/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 9/22/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 10/27/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 10/27/2021 | APPLICANT |
| Issued | 1/4/2022 | APPLICANT |
| CofO in Progress | 1/5/2023 | JON MCHUGH |
| CofO Issued | 1/10/2023 | JOHN JANSON |
| Permit Finaled | 1/10/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2021 | NAZILA NOORIFAR |
| Roof/Waste drainage to street | Cleared | 10/4/2021 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 10/4/2021 | NAZILA NOORIFAR |
| ZI | Cleared | 10/12/2021 | PABLO ESTRADA |
Contact Information
| Contractor | Best Builders Group; Lic. No.: 768777-B | 6911 TOPANGA CYN #203 CANOGA PARK, CA 91303 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/9/2022 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 2/10/2022 | Corrections Issued | SEAN HAUPT |
| Footing/Foundation/Slab | 2/10/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/22/2022 | Partial Approval | SEAN HAUPT |
| Green Building Rough | 2/22/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 2/22/2022 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/4/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/11/2022 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 4/11/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 4/11/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 4/11/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 4/15/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2022 | Approved | SEAN HAUPT |
| Insulation | 4/26/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 4/26/2022 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 5/6/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 6/3/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 6/3/2022 | Not Ready for Inspection | SEAN HAUPT |
| Underground Mechanical | 6/3/2022 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/22/2022 | Approved | SEAN HAUPT |
| Final | 9/22/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 9/22/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 9/22/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 9/22/2022 | Approved | SEAN HAUPT |
| Final | 1/5/2023 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 1/5/2023 | Approved | JON MCHUGH |