7840 W 81ST ST 90293
Certificate Information: 7840 W 81ST ST 90293
- Application / Permit
- 21014-20000-04189
- Plan Check / Job No.
- B21VN11088
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) SFD TO CREATE A NEW BEDROOM, REMOVE NON-LOAD BEARING WALL BETWEEN KITCHEN & LIVING ROOM, REDUCE DECK AND EXTERIOR ALTERATIONS TO INFILL WINDOWS AND DOORS. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 8/26/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 12/1/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 12/21/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 1/12/2022 | ALFREDO JARA |
| Building Plans Picked Up | 1/12/2022 | APPLICANT |
| Issued | 1/20/2022 | APPLICANT |
| CofO in Progress | 4/15/2022 | RICHARD STEINBACH |
| Permit Finaled | 4/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/19/2022 | DANIEL ORRANTE |
| CofO Issued | 4/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/27/2021 | VALERIA CEJA |
| Grading Pre-Inspection | Cleared | 11/3/2021 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 11/18/2021 | NIKTA MOUSAVI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 1/26/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 1/26/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/26/2022 | Approved | BOBBY KEY |
| Shower Pan | 1/26/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 1/27/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 1/27/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 1/27/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 1/27/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 2/2/2022 | Approved | BOBBY KEY |
| Insulation | 2/2/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 2/2/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 4/6/2022 | Approved | BOBBY KEY |
| Final | 4/6/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 4/6/2022 | Approved | BOBBY KEY |
| Green Building Final | 4/6/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 4/6/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 4/6/2022 | Approved | BOBBY KEY |
| Final | 4/13/2022 | Conditional Approval | BOBBY KEY |
| HVAC-Final | 4/13/2022 | Approved | BOBBY KEY |