7105 N PENFIELD AVE 91306
Certificate Information: 7105 N PENFIELD AVE 91306
- Application / Permit
- 21014-20000-04187
- Plan Check / Job No.
- B21VN11084
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20'-3" DETACHED GARAGE AND ADD 16'-3" X 21'-8" TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/13/2021
- Issuing Office
- Current Status
- CofO Issued on 7/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/29/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/1/2021 | RAPHAEL ROSAS |
| Issued | 12/13/2021 | APPLICANT |
| Building Plans Picked Up | 12/16/2021 | APPLICANT |
| CofO in Progress | 6/30/2022 | STEVEN BACK |
| Permit Finaled | 7/5/2022 | JOHN JANSON |
| CofO Issued | 7/5/2022 | JOHN JANSON |
| Permit Finaled | 7/5/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/31/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/1/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 11/21/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/30/2021 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 1/7/2022 | Not Ready for Inspection | STEVEN BACK |
| Pre-Inspection | 1/7/2022 | Partial Inspection | STEVEN BACK |
| Sewer | 1/7/2022 | Not Ready for Inspection | STEVEN BACK |
| Sewer | 1/18/2022 | Approved | STEVEN BACK |
| Underground Mechanical | 1/18/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 1/24/2022 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 2/1/2022 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 2/4/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2022 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 3/18/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 3/18/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 3/18/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 3/18/2022 | Approved | STEVEN BACK |
| Green Building Rough | 3/24/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/24/2022 | Partial Approval | STEVEN BACK |
| Insulation | 3/30/2022 | Corrections Issued | STEVEN BACK |
| Insulation | 4/5/2022 | Not Ready for Inspection | JUSTIN HAWLEY |
| Insulation | 4/7/2022 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 4/11/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 5/5/2022 | Approved | STEVEN BACK |
| Shower Pan | 5/5/2022 | Approved | STEVEN BACK |
| Final | 6/16/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 6/16/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/16/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 6/16/2022 | Approved | STEVEN BACK |
| Final | 6/30/2022 | OK to Issue CofO | STEVEN BACK |