6524 W OLYMPIC PL 90035

Certificate Information: 6524 W OLYMPIC PL 90035

Application / Permit
21014-20000-04186
Plan Check / Job No.
B21VN11077
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADDITION OF A 84 SQ. FT. PATIO COVER TO THE (E) GARAGE. WORK SHALL CONFORM TO P/BC 2020-006.
Permit Issued
Issued on 10/1/2021
Issuing Office
Current Status
Issued on 10/1/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/17/2021 APPLICANT
Assigned to Plan Check Engineer 8/18/2021 COLIN LOREDO
Corrections Issued 8/19/2021 COLIN LOREDO
Plan Check Approved 9/23/2021 COLIN LOREDO
Building Plans Picked Up 9/27/2021 APPLICANT
Issued 10/1/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/30/2021 WALLIE JONG
HPOZ Cleared 9/8/2021 JONATHAN KAPLAN
Eng Process Fee Ord 176,300 Cleared 9/14/2021 WALLIE JONG

Contact Information

Contractor Aldan Construction & Remodeling Inc; Lic. No.: 1030243-B 8549 WILSHIRE BLVD #1458      BEVERLY HILLS, CA 90211

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/19/2021 Approved STUART CHAPMAN
METHANE-Barrier 10/19/2021 Approved STUART CHAPMAN
METHANE-Subgrade 10/19/2021 Approved STUART CHAPMAN
METHANE-Rough 11/4/2021 Not Ready for Inspection JOSE AVILA
Wood Frame 11/4/2021 Not Ready for Inspection JOSE AVILA
METHANE-Rough 11/10/2021 Corrections Issued JOSE AVILA
Wood Frame 11/10/2021 Corrections Issued JOSE AVILA
Drywall Nailing 2/2/2022 Partial Inspection JOSE AVILA
Final 2/2/2022 Not Ready for Inspection JOSE AVILA
METHANE-Final 2/2/2022 Approved JOSE AVILA
METHANE-Rough 2/2/2022 Approved JOSE AVILA
Smoke Detectors 2/2/2022 Approved JOSE AVILA
Wood Frame 2/2/2022 Not Ready for Inspection JOSE AVILA