4734 N TOBIAS AVE 91403

Certificate Information: 4734 N TOBIAS AVE 91403

Application / Permit
21014-20000-04183
Plan Check / Job No.
B21VN11042
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMO ALL INT. AND EXT. WALLS EXCEPT FOR 2 LF AT NORTH SIDE AND ERECT A 40'-0" x 83'-0" ONE-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND PATIO COVER; AUTOMATIC SPRINKLERED SYSTEM IS REQUIRED; ALL WORK PER ENGINEERING DESIGN
Permit Issued
Issued on 10/27/2021
Issuing Office
Current Status
CofO Issued on 7/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 SEAN SHAHMIRI
Corrections Issued 9/20/2021 SEAN SHAHMIRI
Quality Review Completed 10/5/2021 OMID HEDAYAT
Building Plans Picked Up 10/6/2021 APPLICANT
Applicant returned to address corrections 10/18/2021 SEAN SHAHMIRI
Plan Check Approved 10/27/2021 SEAN SHAHMIRI
Issued 10/27/2021 APPLICANT
CofO in Progress 7/13/2022 MISAEL ESPARZA
Permit Finaled 7/30/2022 DEROLD HAUFF
CofO Issued 7/30/2022 DEROLD HAUFF
Permit Finaled 7/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/23/2021 CARLOS AGUILERA
Permit Cleared 9/23/2021 CARLOS AGUILERA
Sewer availability Cleared 9/23/2021 CARLOS AGUILERA
Low Impact Development Cleared 10/5/2021 LONDY ALVARADO
ZI Cleared 10/5/2021 ANNA VIDAL
Roof/Waste drainage to street Cleared 10/8/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/10/2021 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/7/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 1/8/2022 Off-Hour Fees Due
Underground Mechanical 1/8/2022 Approved CARLOS MATAMOROS
Underground Mechanical 1/11/2022 Partial Inspection MISAEL ESPARZA
Footing/Foundation/Slab 1/18/2022 Approved MISAEL ESPARZA
Deputy Reinf. Concrete 1/21/2022 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 2/7/2022 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 2/7/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/10/2022 Conditional Approval MISAEL ESPARZA
Green Building Rough 2/10/2022 Approved MISAEL ESPARZA
MERV13>=Rough 2/10/2022 Approved MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 2/10/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/16/2022 Approved ASHLEY THOMPSON
Insulation 2/16/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 2/16/2022 Approved ASHLEY THOMPSON
Drywall Nailing 2/25/2022 Approved MISAEL ESPARZA
Final 7/5/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 7/5/2022 Approved MISAEL ESPARZA
MERV13>=Final 7/5/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/5/2022 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 7/5/2022 Corrections Issued MISAEL ESPARZA
Final 7/12/2022 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 7/12/2022 Approved MISAEL ESPARZA
Smoke Detectors 7/12/2022 Approved MISAEL ESPARZA