8826 N TYRONE AVE 91402
Certificate Information: 8826 N TYRONE AVE 91402
- Application / Permit
- 21014-20000-04176
- Plan Check / Job No.
- B21VN11035
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Garage Conversion to be added to (E) Accessory dwelling unit per Ordinance
- Permit Issued
- Issued on 11/24/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2021 | MONICA RAMIREZ |
| Corrections Issued | 8/18/2021 | MONICA RAMIREZ |
| Plan Check Approved | 11/21/2021 | MONICA RAMIREZ |
| Issued | 11/24/2021 | APPLICANT |
| CofO in Progress | 1/25/2022 | GREGG CUMMINGS |
| Permit Finaled | 2/17/2022 | MICHAEL SMITH |
| CofO Issued | 2/17/2022 | MICHAEL SMITH |
| Permit Finaled | 2/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/13/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/7/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/7/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 12/7/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/16/2021 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 12/16/2021 | Not Ready for Inspection | WILLIAM WREN |
| Wood Frame | 12/16/2021 | Not Ready for Inspection | WILLIAM WREN |
| Insulation | 12/17/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/20/2021 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 12/20/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 12/20/2021 | Approved | GREGG CUMMINGS |
| Insulation | 12/22/2021 | Not Ready for Inspection | DAVID MATSON |
| Insulation | 12/27/2021 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/27/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 12/30/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/30/2021 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/4/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 1/4/2022 | Approved | GREGG CUMMINGS |
| Insulation | 1/4/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/4/2022 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 1/10/2022 | Approved | GREGG CUMMINGS |
| Final | 1/18/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/18/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 1/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 1/25/2022 | Approved | GREGG CUMMINGS |
| Final | 1/25/2022 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 1/25/2022 | Approved | GREGG CUMMINGS |
| HVAC-Final | 1/25/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 1/25/2022 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 1/25/2022 | Approved | GREGG CUMMINGS |